Two projects in one
Text Desiree PenningsImage Homij

Heerlen Town Hall and Municipal Offices
The coronavirus pandemic may seem a distant memory, but it recently caused immense problems for the construction industry. Meetings had to be held remotely, building materials could not be delivered, and then there was the blockage of the Suez Canal. Homij faced all of these issues while installing the electrical and mechanical systems in Heerlen’s Municipal Offices and Town Hall. Even so, it delivered a successful project with a stunning end result.
The renovated Town Hall in Heerlen originally dates from 1942 and was designed by architect Frits Peutz. It stands next to the new Municipal Offices, designed by Mecanoo architecten. The two separate buildings nevertheless form a cohesive whole, framed by a green public space. The project comprised two phases: first, the old Municipal Offices were demolished, and the new building was completed in December 2021. The Town Hall was then renovated, with work completed shortly before the summer construction holiday.

Municipal Offices
The Municipal Offices is a restrained building with white limewashed brickwork and window frames, complementing the neighbouring Town Hall. At ground-floor level, the two buildings are connected by a central entrance. Inside, the new Municipal Offices has an atrium extending from the ground floor to the fifth floor. This presented a challenge for climate control, says Frank Vossen, project manager for electrical and mechanical installations at Homij. “Heat from the ground floor must not rise all the way to the fifth floor. To prevent this, we installed low-temperature underfloor heating and ensured the right air balance on every level, with separate supply and extract air.”
The atrium also posed a fire-safety challenge, as sprinklers had to be installed throughout. A 130 m3 water tank was built in the existing basement of the Municipal Offices. “The basement structure is the only part of the building that was retained,” says Vossen. “It houses the plant rooms as well as the sprinkler tank.”

Town Hall
Once the Municipal Offices had been completed, it was the Town Hall’s turn. It still contained many heritage features, including details in the floors and ceilings. This historic character had to be preserved, while the building services also needed a complete upgrade. Heating and cooling are supplied by Mijnwater, a sustainable energy provider that uses former mine workings as a source and buffer. Heat pumps bring the temperature to the required level. Vossen says: “Using low temperatures means you have to insulate the building much better. We then looked at each room individually to determine the best way to provide heating: underfloor heating, wall heating or convectors. We used a different method in each room. Where there was a heritage floor, for example, we incorporated the solution into the ceilings.”
Unfortunately, not all the existing ceilings could remain exposed. Air ducts and cable trays had to be concealed. Where new building services had to be installed, a new ceiling was fitted. The old one was retained, however, in case of future renovations. Vossen says: “The municipality did not want to compromise on comfort, so this was necessary for the ventilation and other systems. There can sometimes be tension between architecture and building services.”

Intensive consultation
For this project, Heerlen municipality opted for the UAV-GC contract form. This meant that the project team, comprising Mecanoo, Jongen, ABT and Homij, translated the client’s requirements into a detailed design. The collaboration went smoothly, according to Vossen: “Mecanoo is a world-renowned architecture practice that details everything ‘down to the last screw’ and sets high standards. Because we were part of the same team, we were able to coordinate everything. We reached a good solution on every point. The consultation process was intensive. Because it was during the pandemic, 80% of meetings were held online, and material shortages caused delays. This brought its challenges, but we hear from the building’s employees that they are very satisfied. Everything is working exactly as it should.”
Question about this story? Ask your question
Who worked on it
Heerlen town hall and municipal offices in Heerlen
- ArchitectMecanoo architecten
- Main contractorBouwbedrijf Jongen
- Adviseur constructies en installatiesABT
- Building servicesHomij
- warmte en koudeMijnwater
Keep following this
Get an email when a new story is published. No account needed.
- ProjectHeerlen town hall and municipal offices
- SubjectProjects
- CompanyMecanoo architecten
- CompanyBouwbedrijf Jongen
- CompanyABT
- CompanyHomij
- CompanyMijnwater


















