Home-grown air ducts

Text Lieke BousemaImage Nijburg Industry Group

In navolging van de rechthoekige kanalen, levert en monteert Nijburg Klimaattechniek circa 3.000 m¹ spiraalbuis.
In navolging van de rechthoekige kanalen, levert en monteert Nijburg Klimaattechniek circa 3.000 m¹ spiraalbuis.

Around 4,000 m² of rectangular ductwork and 3,000 linear metres of circular ductwork for the new UMCG Operating Centre

At the heart of the University Medical Center Groningen (UMCG), work is under way on a new Operating Centre with two hybrid operating theatres, four general-purpose operating theatres, two intervention rooms, a CT room and ten recovery rooms. As the hospital will remain fully operational throughout the work, specialist contractors are essential. This also applies to the supply and installation of the air ducts and ventilation components. Hanab Installation Technology awarded this important contract to Nijburg Klimaattechniek, which has previously delivered the ventilation systems at Isala in Meppel, Medisch Centrum Leeuwarden and Nij Smellinghe in Drachten.

Nijburg Klimaattechniek is part of the Nijburg Industry Group, which focuses on producing, supplying and installing complete solutions for a healthy and comfortable indoor climate. “For the new UMCG Operating Centre, we are responsible for producing, supplying and installing around 4,000 m² of rectangular ductwork, including 1,380 m² of heavy-gauge ductwork,” says Robert Degen, Project Manager at Nijburg Klimaattechniek. “The heavy-gauge ducts ensure vibration-free and quiet operation. They are also fire-protected to maintain their function. Should an emergency occur, work can continue in the operating theatres.” Some of the heavy-gauge ductwork has been insulated with 30 mm of fire-resistant insulation, while the standard supply ducts have been insulated with 25 mm of mineral wool.

Nijburg is delivering the ventilation systems for the new Operating Centre.

Following the rectangular ductwork, Nijburg Klimaattechniek is also supplying and installing around 3,000 linear metres of spiral duct, Degen says. The family-owned business from Midden-Groningen is also installing the supplied components, including reheaters, swirl diffusers, variable air volume controllers and fire dampers. “All the ducts meet Luka Air Leakage Class C and Cleanliness Class H requirements, and are carefully cleaned and sealed after manufacture. We also work to a strict delivery and drilling schedule to avoid logistical and installation disruption. Large ducts are needed because a high volume of air must be replaced in the relatively small operating theatres. This calls for careful coordination with the main and subcontractors. All the installation components have therefore also been modelled and clash-checked in 3D/BIM in advance. All the operating theatres are being built as Faraday cages, with a mounting rail installed at ceiling level by a single contractor. We will then suspend our air ducts from it.” The ventilation systems are due to be handed over in April 2025.    

A business enquiry for Kooi Camerabewaking? Get in touch

Who worked on Operatiecentrum UMCG

  1. construction workMedicomZesMentioned in A complex project in a medical centre that operates 24/7
  2. installerHanab Installation TechnologyMentioned in A complex project in a medical centre that operates 24/7
  3. adviceRoyal HaskoningDHVMentioned in A complex project in a medical centre that operates 24/7

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectOperatiecentrum UMCG
  • ThemeHealthy indoor air
  • SubjectDuctwork
  • CompanyKooi Camerabewaking
Share this article

Follow Installatie & Bouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.