Prefabricated ventilation: from cast-in channels to complete plant rooms
Text Els HekkenbergImage Interduct

An apartment block contains tens of metres of ventilation ductwork. Traditionally, most of it is cut to size and assembled on site. There is another way. More and more of this work is moving to the factory, where conditions are better and dimensions can be specified more accurately.
“Almost everything can be prefabricated,” says Ruud van Kasteren, commercial director at Robé, Interduct’s manufacturing company. “But it is important to work to certain standards.” Without those standards, all you are doing is moving bespoke work from the building site to the workshop.

From cast-in channels to installation lengths
It starts with the cast-in channels. These are no longer measured and cut on site, but delivered directly to the concrete factory and incorporated into the floor there. The same principle applies to the communal ductwork in apartment blocks. It comes off the production line in installation lengths, complete with insulation and branches. On site, the installer only has to secure it with brackets and connect the sections.
The next step is the plant room itself. Traditionally, this is built on site for each dwelling, which is highly labour-intensive. According to Van Kasteren, the entire room can be delivered as a single prefabricated module, incorporating ventilation, heating, hot water and energy generation. The installer then only has to connect the system.

More accurate than manual work
The benefits are not limited to speed. In a factory, work takes place in better conditions, using standard dimensions and based on designs modelled in 3D in advance. “There are more disruptions on site,” says Van Kasteren. “Quite simply, there is a greater chance of mistakes when you do everything on site.” Designing and connecting prefabricated components reduces that risk.
The trade-off is more intensive preparation, especially for the first project in a partnership. The parties need to sit down together earlier, and there is no longer room for last-minute changes. Van Kasteren says the investment pays off elsewhere. “With traditional construction, every project starts from scratch. With prefabrication, on the other hand, 80 to 90 per cent of the technical work has already been worked out after the first project. So you can save the time that you would otherwise spend again and again on the preparatory work by using prefabricated solutions.” Both the development and installation processes are faster.

Thinking like a manufacturer, not an installer
Prefabrication can be approached from two angles. Installation companies come from the field and look for ways to reduce the time needed for final assembly on site. Robé looks at it from a manufacturing perspective. “We approach it more from the standpoint of a manufacturer in the market,” says Van Kasteren. “That leads to different insights, solutions and processes.” The company’s role is deliberately defined. “Co-making with installers is an important principle. And, for example, we don’t make MVHR units or heat pumps, but we make sure they are delivered intelligently and prefabricated to where they need to be.” This includes cast-in channels and risers, rooftop heat pump enclosures and plant rooms, delivered to site ready to install. This suits a building site that is increasingly becoming an assembly area, as well as the shift towards industrialised construction that the sector is already making. With a shortage of skilled workers and a major housing deficit, the question, according to Van Kasteren, is not whether things need to change. “Given everything happening in the market, we can’t keep doing what we’ve always done. And prefabrication is the answer.”
Have a business enquiry for Interduct? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeHealthy indoor air
- SubjectVentilation
- CompanyInterduct