Oldenelerbroek Zwolle: all-electric homes in Zwolle-Zuid
Text Lieke BousemaImage Breman Techniek Zwolle

The renovation takes around 15 working days per home. A substantial amount of sustainable renovation work is carried out during this period, says Project Manager Diederik de Jong. “The thermal envelope of each home is significantly improved by installing triple glazing and sealing gaps and cracks. The homes are also getting a new front door and a heat recovery ventilation system.” Breman Techniek Zwolle is installing an all-electric heat pump in every home. “The air-to-water heat pump is connected to the existing central heating system. The system is then hydraulically balanced based on the heat demand and radiator types in each room.”

151 homes, 41 panel layouts
To sustainably offset the additional electricity consumption from the heat pumps, PV panels are being installed on all homes. The target is to generate around 3,000 kWh per home, says De Jong. “As around half of the homes already have a PV system, the right capacity has been determined for each home. Naturally, this takes account of the roof orientation and the installation of system components such as roof penetrations and heat pump outdoor units. We have drawn up no fewer than 41 different panel layouts for the 151 homes!”
At the request of the Welstandscommissie, all heat pump outdoor units were sprayed with an anthracite-grey two-pack coating. The units were then prefabricated at the Breman Techniek warehouse and fitted with brackets and isolators. “Because the roofs are difficult to access, they are transported to the site in large batches of 15-20 and lifted directly into position on the roof using a telehandler.”
Careful power distribution
“All kitchens are being fitted with an induction hob and, if not already present, a recirculating cooker hood,” says De Jong. “The old meter cupboards are also being replaced with new ones with a higher-capacity connection (3x 25A). We have been through an extensive process with Enexis to coordinate the infrastructure for this.” As Enexis will not begin upgrading the local electricity network until the end of this year, Breman Techniek Zwolle has carefully allocated the electricity available to the homes. “Residents are being asked to keep the heat pumps running as steadily as possible. The anti-legionella function of the hot water cylinders will also be activated per block of homes during the night.” The work is due to be completed in April 2025.