Plug-and-play electrical installation for the Palace of Justice in Den Bosch: smart, fast and flexible for the future

Plug-and-play electrical installation for the Palace of Justice in Den Bosch: smart, fast and flexible for the future

Under the motto ‘sustainable justice’, the Palace of Justice in Den Bosch is undergoing a major renovation. The main aim is to make the working environment of the East Brabant District Court, the ’s-Hertogenbosch Court of Appeal and the Public Prosecution Service more sustainable and bring it into line with the requirements of today and tomorrow.

For the corridors, Isolectra has designed a 5-core, 3-phase Wieland flat cable system, installed against the wire basket tray.

The work is being carried out by the Dura Vermeer and Croonwolter&dros consortium and began in April 2021. “As the Palace of Justice will remain in use during the renovation, it was decided to divide the work into phases,” says Michel Molenaar, project manager at Croonwolter&dros. “The third and final renovation phase began in early September and is due for completion in June 2023. In each section of the building, following a design by Fokkema & Partners Architecten, dark, long corridors and small offices are being replaced by open, transparent routes and spaces. Comfortable, bright, contemporary workspaces are being created throughout the building. Acoustic insulation is also being improved, so staff can work on their cases in peace and with full concentration. The use of partition walls makes it easy to increase or reduce the size of workspaces. In addition, the new layout will provide space in future for related justice organisations, such as the Immigration and Naturalisation Service, the Child Care and Protection Board and the Repatriation and Departure Service.”

Plug-and-play wherever possible

To bring sustainability and (workplace) comfort at the Palace of Justice to the highest possible level, new building services systems, including a heat pump, are being installed. “This is an important step towards an all-electric future,” says Molenaar. “All the building services installations are also being renewed. Wherever possible, we are using Isolectra’s plug-and-play technology.”

Molenaar says he embraced plug-and-play installation back in 2007. “Mainly because it saves a great deal of installation time without compromising quality or service life. In recent years, Isolectra and I have looked at ways to improve and speed up installation processes. Croonwolter&dros continues to reap the benefits of that work. The Palace of Justice is another example, with both the lighting installation and electrical infrastructure being built using plug-and-play systems. As the renovation is being carried out under a UAV-GC contract, we must be able to guarantee the quality of the installations for at least 10 years. Thanks to Isolectra’s Wieland plug-and-play installations and our extensive expertise in plug-and-play installation, that is no problem at all.”

Isolectra initially developed a plug-and-play solution for the lighting in the office areas.

Repetitive layouts

“The Palace of Justice has many repetitive layouts,” says Frans van Loon, Key Account Manager at Isolectra. “This makes the building particularly well suited to plug-and-play installation. Plug-and-play installation also meets the need for flexibility. The installation can easily be adapted to each layout. For example, when partition walls are moved, the Wieland cables can simply be disconnected and adapted to the new arrangement.”

Separate power supply and DALI signal

Isolectra initially developed a plug-and-play solution for the lighting in the office areas, says Van Loon. “We fitted the lighting with a separate Wieland GST18i3® interconnecting cable for the power supply and a Wieland GST15i2® DALI interconnecting cable, which connects the luminaires to a Priva monitoring and control unit in the corridor. Using separate Wieland cables for the power supply and DALI signal means the luminaires can easily be connected across different circuits, offering even greater flexibility.”

3-phase flat cable system

For the corridors, Isolectra has designed a 5-core, 3-phase Wieland flat cable system, installed against the wire basket tray. “The flat cable system provides a constant power supply to the emergency lighting,” says Molenaar. “It also allows us to switch the corridor lighting.” Van Loon adds: “The tap-off points on the flat cable can easily be set to phase 1, 2 or 3. A Wieland cable can also be plugged straight in, for example to supply power to the lighting.”

All plug-and-play Wieland components are delivered by wholesaler Technische Unie to each section of the building and each floor. This enables Croonwolter&dros installers to work quickly without ever running short of components.    

Have a business enquiry for Isolectra BV? Get in touch

Who worked on it

Paleis van Justitie in Den Bosch, renovation

  1. pluggable systemsIsolectra
  2. consortiumDura Vermeer
  3. consortiumCroonwolter&dros
  4. architectFokkema & Partners Architecten
  5. wholesaleTechnische Unie

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectPaleis van Justitie
  • ThemeBuilding electrical systems
  • SubjectGeneral
  • CompanyIsolectra BV
  • CompanyDura Vermeer
  • CompanyCroonwolter&dros
  • CompanyFokkema & Partners Architecten
  • CompanyTechnische Unie
Share this article

Follow Installatie & Bouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.