Clean air ducts on show
Text Desiree PenningsImage Airpro

Ausnutria is building a new factory in Heerenveen
In Heerenveen, Ausnutria is building a new, sustainable factory for semi-finished baby and toddler food products. When the building, which is more than forty metres high, is commissioned at the end of this year, it will be completely free of CO2 and nitrogen emissions, with a gas-free production process. Airpro is also a forward-thinking company committed to sustainability. It is therefore no surprise that Airpro supplied and installed the air ducts for the factory and office area.
The air ducts for Ausnutria in Heerenveen were thoroughly cleaned, both inside and out, before being delivered as a kit to the correct Luka cleanliness class (M). After installation, they were carefully covered every day to prevent possible contamination. “This was a large-scale and exceptionally demanding process, particularly because all the process ducts for medium- and high-care applications are made from 304 stainless steel,” says Marcel Schoof. Schoof is co-owner of Airpro, alongside Bartho Sterrenburg and Jacques Crebolder. “In the office area, by contrast, we used standard Sendzimir-galvanised ducts.”

The 304 stainless steel ducts were bent on computer-controlled press brakes and then spot-welded. A substantial proportion of the ducts was prefabricated, making installation on site significantly quicker. The grilles were also fitted to the ducts at the factory. The schedule was particularly tightly organised during the initial stages. Thanks to effective coding and internal transport, all the air ducts were delivered and installed at the right time and on the right level. Schoof adds: “We prepared a specific ductwork booklet in advance covering the duct sections, suspension and fixing materials, and submitted sample pieces to the client for approval.”
Exposed ducts
The services will remain visible once the building is complete. This made the work during the shell construction phase different from usual, says Sterrenburg. “It had to be carried out with the greatest possible precision. We make exposed ducts quite often, but not in this size or quantity. Normally, there is some tolerance in the duct, and we adjust it to fit at the very end. That was not possible here. We manufactured everything from the drawings, incorporating the tolerances. The products were delivered clean, to the required cleanliness standard, as a kit.” The materials were secured in advance, so the client could be sure everything was in stock and there would be no supply problems.

Extensive preparation
Extensive preparation went into this project. The client, ALTUM Technical Solutions, modelled the services using the Revit methodology in an integrated BIM model. Working closely with ALTUM Technical Solutions and its consultant, CLAFIS Ingenieus, Airpro prepared the project down to the smallest detail. This helped prevent errors during installation, as all staff were fully aware of the requirements. “We communicated carefully and considered the preparations well in advance, which allowed the installation process to run smoothly,” Sterrenburg adds. “Although this way of working took a great deal of time and energy during the preparation stage, it paid off. In collaboration with ALTUM Technical Solutions, we achieved a very positive working relationship, a tight but achievable schedule and an end result that satisfied everyone. We delivered an excellent project, installed in one continuous flow and on schedule.”
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeHealthy indoor air
- SubjectGeneral