Completely new building services for Noorderpoort in just eight weeks: ‘Comfortable and energy-efficient’

One of Noorderpoort’s schools in Groningen underwent a complete overhaul in July and August, carried out by vanPanhuis Hoogeveen, part of Top Installatiegroep.
At the start of the year, many of the 70 classrooms at this ROC site still had no ventilation system. A window had to be opened in each classroom to provide ventilation. That is now a thing of the past, following the complete renewal of the school’s heating, cooling and ventilation systems.

“Ventilation is now controlled by CO2 levels in each classroom, so the air exchange rate is automatically adjusted to the number of people in the room. Comfortable, fresh and energy-efficient,” explains project manager Paul Peet on behalf of vanPanhuis Hoogeveen. In April, Noorderpoort awarded vanPanhuis Hoogeveen the contract to design and install all the mechanical and electrical services, in collaboration with Adviesbureau Winkelman Engineering in Drachten. “The pandemic was already under way, but the school had been planning to tackle the systems before then,” says Peet. “The renewal happened to coincide with the national debate about ventilation in schools.”
Heat pump takes the lead
As well as the ventilation, vanPanhuis Hoogeveen also upgraded the heating and cooling at the school, which has around 3,500 pupils. The traditional central heating system is still in place, but the newly installed heat pump, combined with an additional heat pump, now ‘takes the lead’ in regulating the temperature, in Peet’s words. “Only in really wintry conditions will the central heating system need to provide additional heat to the classrooms.” The four-pipe heat pump system makes it possible to cool or heat individual rooms, or to cool and heat them simultaneously. “For example, when one side of the school has different requirements from the other,” the project manager explains.

BREEAM standard in mind
According to Peet, all the systems were designed and selected with the BREEAM standard in mind. “Energy management and controls are important here. This means the systems must not only deliver good efficiency, but also make it easy for the school to monitor them.” He says the project achieved this very successfully. When the project was completed, the school and vanPanhuis Hoogeveen agreed on a one-year monitoring programme. During the year, the school’s experience of the new systems will be discussed at four review meetings. At the first meeting, the project manager says, the school reported being very satisfied.

Improved lux levels and UGR
The electrical work on this project focused mainly on the lighting. The old fluorescent lighting was replaced with LED throughout the school. Peet says this has greatly improved the overall light levels. “This is thanks to improved lux levels and UGR,” he explains. “There were also a lot of shadowed areas, which have now disappeared. LED therefore not only saves energy, but also contributes to better learning outcomes.”
vanPanhuis completed the entire project in eight weeks. The final finishing touches were made on the Saturday before the pupils returned to school on Monday. “Despite the time pressure, we were able to deliver a high-quality project. This was thanks to thorough preparation and excellent collaboration with Noorderpoort and Winkelman Engineering,” the project manager concludes, satisfied.