Meter cupboards go off-site, speeding up schedules

Enexis Netbeheer and Van Wijnen are rolling out prefabricated meter cupboards, which are installed at the start of the construction process. This saves time on schedules and improves safety on site. Enexis Netbeheer will offer the concept to construction companies from spring 2020.
Tilburg in North Brabant is the first to have a prefabricated meter cupboard, at the Willemsbuiten construction site. Earlier pilots in Assen and Groningen were also successful, covering more than 200 homes. The meter cupboard is installed once the ground floor has been laid, when, for example, painters and bricklayers are not yet on site. The contents of the cupboard are unchanged, and are installed and assembled by the contractor. Enexis Netbeheer then connects it on site.
Safer and faster
“Previously, we would first arrange a temporary construction connection for the site,” says Enexis Netbeheer consumer manager Lotte Breunesse, describing how things used to work. “We would return shortly before handover to put the permanent connection in place. With the prefabricated meter cupboard, that is no longer necessary. The contractor can use it during construction, and the residents can use it once they move in.” There are also safety benefits, for example because the number of cables can be reduced. This means less risk of tripping. “Previously, we had a large number of cables spread across the site. This number has been greatly reduced because each home already has its own power connection.”

The project partners are Mijnaansluiting.nl, Enexis Netbeheer, Van Wijnen and De Verbinding BV, a social enterprise employing deaf carpenters.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeIntegrated construction and building services
- SubjectGeneral