New pharmaceutical centre for AVL and NKI: Collaboration delivers high-quality handover

New pharmaceutical centre for AVL and NKI: Collaboration delivers high-quality handover

Following an extensive commissioning and handover phase, the new pharmaceutical centre was formally handed over to Antoni van Leeuwenhoek Ziekenhuis (AVL) and Nederlands Kanker Instituut (NKI) in Amsterdam in mid-April 2020. As part of an installation consortium with Climatech, Breman Utiliteit Zwolle supplied and installed all the medical gas systems for the new building, as well as its mechanical, electrical, control, cleanroom and VHP systems.

The project covered a total area of approximately 7,000 m² and took one year to complete. It was preceded by an extensive verification phase, explains Roy Voss of DVE Project Support, who acted as project manager on behalf of the Breman and ClimaTech consortium. “During the verification phase, we worked closely with AVL and consultant Royal HaskoningDHV to review the technical design and all the underlying assumptions. The aim was to draw on Breman and ClimaTech’s practical expertise to identify omissions and optimise the design where necessary. Examples include the use of a busbar trunking system and a decentralised VHP system. The phase proved its worth: the project was handed over on time, with minimal disruption and few outstanding items.”

Building services

Most of the building services are located on the fifth floor, Voss explains. “This is where the central air handling units, compressed air system, heating and cooling manifolds and control cabinets are located. The pharmaceutical centre uses the heating and cooling generated by the existing AVL buildings for climate control. The chosen distribution system combines, among other things, chilled ceilings and ventilation systems. This also involved establishing the correct air pressure hierarchy, and monitoring it, on both cleanroom floors.”

High standards

The design, construction and handover were all subject to stringent requirements. The cleanrooms and sterile areas, for example, had to comply with strict GMP guidelines, requiring an extensive process of commissioning, validation and reporting. “The coronavirus was an additional challenge,” says Voss. “We had to adjust our schedules, stagger breaks throughout the day and actively separate construction traffic flows. The work was also carried out in smaller groups, enabling us to safeguard the health and safety of everyone on site at all times.” 

Question about this story? Ask your question

Wie aan Farmaceutisch centrum Antoni van Leeuwenhoek Ziekenhuis Amsterdam werkte

  1. installerBreman Utiliteit ZwolleMentioned in Plug-in installations add significant value at the Antoni van Leeuwenhoek Hospital’s pharmaceutical centre
  2. wholesaleTechnische UnieMentioned in Plug-in installations add significant value at the Antoni van Leeuwenhoek Hospital’s pharmaceutical centre
  3. building services consortiumClimatechIn this story
  4. adviserRoyal HaskoningDHVIn this story
  5. project managerDVE Project SupportIn this story
  6. verlichtingsarmaturenMaas & HagoortMentioned in Antoni van Leeuwenhoek Hospital: Plug-in installations add significant value to pharmaceutical centre

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectFarmaceutisch centrum Antoni van Leeuwenhoek Ziekenhuis Amsterdam
  • ThemeIntegrated construction and building services
  • SubjectGeneral
  • CompanyClimatech
  • CompanyRoyal HaskoningDHV
  • CompanyDVE Project Support
Share this article

Follow Installatie & Bouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.