North Sea Building Scheveningen:

From office building to luxury hotel.
In December, hotel chain Fletcher Hotels opened a new, exclusive 4-star hotel in Scheveningen. The hotel occupies the former North Sea Building office block and has 116 hotel rooms, an à la carte restaurant and a welcoming hotel bar. Basic-Fit has a gym on the ground and first floors, where various works were also carried out. Kemp Installatie BV was responsible for all the mechanical and plumbing installations on the project, commissioned by building owner GDW BV. These ranged from heating, cooling and ventilation to the gas installation, drinking water pipes, foul water drainage and sanitary installations, including the associated.
“Working with installation consultants Overdevest Adviseurs and project managers Van Reisen Bouwmanagement & Advies, we developed the preliminary installation design into a detailed design,” says Paul Zuidervaart, Sanitary Installations Project Manager at Kemp Installatie BV. “We surveyed which installations could be retained. For example, two existing air handling units in the basement were refurbished, fitted with DX coils and connected to air-source heat pumps that heat and/or cool the incoming outdoor air.” The air ducts in the service risers were also retained. “The same applies to the climate control systems on the ground and first floors. Both floors are heated by a central heating boiler in combination with façade radiators. We installed an air curtain at the main building entrance.” Because hotel rooms require different climate control and sanitary installations from offices, all the installations on the hotel floors were replaced. “VRF units provide heating and cooling in the rooms. A scheduled setback period helps control energy use by automatically returning the systems to their basic settings when the rooms are unoccupied.”
Kemp Installatie BV began stripping out the office spaces at the end of 2019. This posed a challenge, according to Zuidervaart, because several floors remained in use until the start of the building holiday. “New soil stacks also had to be installed for the hotel rooms, and these ran into the gym. We had to create a new main sewer route there with as little disruption as possible. We brought this work forward efficiently when all gyms were closed during the first lockdown.”
Question about this story? Ask your question
Who worked on it
North Sea Building
- building ownerGDW BV
- Mechanical and sanitary installationsKemp Installatie BV
- building services consultantOverdevest Adviseurs
- contract administratorVan Reisen Bouwmanagement & Advies
Keep following this
Get an email when a new story is published. No account needed.
- ProjectNorth Sea Building
- SubjectGeneral
- CompanyGDW BV
- CompanyKemp Installatie BV
- CompanyOverdevest Adviseurs
- CompanyVan Reisen Bouwmanagement & Advies