A unique redevelopment is under way between Rembrandtpark and the A10 ring road in Amsterdam West. In just sixteen months of construction, the anonymous, inward-looking Ringpark building dating from 1967 is being transformed into an open, transparent multi-tenant building with high-quality office space and public amenities, including a coffee bar, staff restaurant, gym and waterside terrace. It is also becoming a highly sustainable building, with a BREEAM-NL ‘Excellent’ rating. The building services technologies installed by Bosman Bedrijven are making a major contribution.

Thomas Hercules, mechanical project manager at Bosman Bedrijven.

Commissioned by property developer Boelens de Gruyter and working as part of a construction team with contractor Dura Vermeer Renovatie Midden West, Bosman Bedrijven is installing the mechanical, plumbing and electrical systems at Rembrandt Park One, including the fire alarm and sprinkler systems and associated controls. “We are a building services contractor focused on expertise and coordination. We work to agreed principles and parameters and help coordinate interfaces across the project,” says Thomas Hercules, mechanical project manager at Bosman Bedrijven. “Our responsibility in the transformation of Rembrandt Park One is to equip the entire building with future-proof systems, working with our co-makers. Most of this responsibility involves setting up processes, designing and engineering the systems, and coordinating the construction work, with the ultimate aim of jointly handing over a high-quality building in spring 2023.”

New systems and structure.

Site surveys, baseline measurements and studies

Making the concrete colossus, which covers around 24,000 m2, suitable for its new uses is no easy task, Hercules stresses. “During the preparatory phase, we carried out several site surveys, baseline measurements and studies in consultation with the building services consultant to determine which systems could be reused. After all, reuse is more sustainable than replacement. However, the findings showed that the systems were too old and not sufficiently future-proof. We therefore switched to a complete renewal.” According to Hercules, the condition of the building itself was even more important than that of its systems. Would the structure provide enough space for the new installations? “Even during the contract formation stage, we investigated the space allocation. The structural framework and existing openings were scanned by the structural engineer and incorporated into a 3D model. This model was an important starting point for the design and engineering. A major risk in a building like Rembrandt Park One is that routes for cable runs, busbar trunking, pipework and air ducts may need to be changed after the contract has been signed. This could happen, for example, because the high sustainability requirements call for greater air volumes and therefore larger air ducts.”

Services zone.

Sustainable climate systems

During the design and engineering phase, Bosman Bedrijven decommissioned all the existing, outdated systems so that the contractor and demolition team could strip out the building. Hercules says this was an interesting point in the project, as it made clear exactly what spaces they had to work with. During the strip-out, all non-masonry materials and systems were removed from the building. High-performance insulation was then installed on the building façade to significantly reduce heating and cooling demand. “The remaining demand is met as sustainably as possible by an aquifer thermal energy storage system with heat pumps. Underfloor heating and cooling were selected as the heat distribution system, alongside climate ceilings that provide even heat and cooling output, ensuring a high level of comfort without draught complaints. These low-temperature heat distribution systems minimise temperature exceedances, helping us meet an important BREEAM requirement.”

A total of four air handling units will be installed to ventilate Rembrandt Park One, with a combined maximum air volume of 133,500 m3/h. “Invisible ceiling grilles will be installed above the perforated panels of the climate ceilings to distribute the air,” says Hercules. “This brings together a smooth ceiling finish and ideal indoor climate conditions. Water-saving sanitaryware is also being used throughout. Shut-off valves on the water supply to the toilet facilities are controlled by occupancy. Water meters are also being installed in the domestic hot water system, so users can see exactly how much water is being consumed in the building management system.” There will be 447 solar panels on the roof. “Lighting at Rembrandt Park One will use LED and be intelligently controlled by time and occupancy. All systems in the offices are also divided into control zones of no more than 40 m2, ensuring optimum flexibility for the building. This also earns valuable BREEAM credits.”

Opportunities and challenges

“It’s fantastic to breathe new life into an old building in this way,” Hercules stresses. “And it’s great to do it with such a large group of people. Just look at how many people are on site and in the office. With so many different stakeholders and individuals involved, communication is a major challenge. Complexity can creep in faster than you realise. For example, changes and other unforeseen matters can have an impact, such as the current rise in material prices. Communication and coordination remain crucial in these situations, and we continue to manage changes and deviations professionally. As long as we keep talking and setting out our expectations to one another, we can always find a solution. This project is proof of that.” 

Question about this story? Ask your question

Wie aan Rembrandt Park One werkte

  1. warmte-en-koude-exploitantEteckMentioned in ATES system with three heat pumps for Rembrandt Park One
  2. complete opwekkingsinstallatieRoodenburgMentioned in ATES system with three heat pumps for Rembrandt Park One
  3. gebouwinstallatieBosman BedrijvenMentioned in ATES system with three heat pumps for Rembrandt Park One
  4. clientRound Hill CapitalIn this story
  5. Construction managementBoelens de GruyterIn this story
  6. architectHofmanDujardinIn this story
  7. contractorDura Vermeer Renovatie Midden WestIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectRembrandt Park One
  • SubjectGeneral
  • CompanyRound Hill Capital
  • CompanyBoelens de Gruyter
  • CompanyHofmanDujardin
  • CompanyDura Vermeer Renovatie Midden West
Share this article

Follow Installatie & Bouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.