State-of-the-art new building for Eurofins in Amersfoort
Text Chris ElbersImage Van Dorp Projecten

To replace and expand its current testing facility in Barneveld, Eurofins Analytico is building a new, state-of-the-art laboratory in Amersfoort Vathorst. Located on Stockholmweg, it will be used for environmental testing of soil, water and other materials from 2026. The building has been designed with a strong focus on sustainability. Recyclable materials are being used, and the nearly gas-free building will be fitted with solar panels.
Eurofins Analytico is part of Eurofins Scientific, the global market leader in bioanalytical testing for food, water, the environment and pharmaceutical products. The state-of-the-art laboratory, with a floor area of over 9,700 square metres, represents a significant expansion of the company’s existing facilities. At the same time, the new building, which will also house offices, a warehouse, cold storage and meeting rooms, will enable the automation of processes. This will further improve the reliability and efficiency of the analyses.

The complete picture
Van Dorp Installaties is responsible for all electrical services, commissioned by main contractor Burgland Bouw, while Van Dorp Projecten is providing the complete mechanical installation. “We’re installing the systems for climate control, plumbing, central heating and chilled water, as well as the facilities required for the use of specific gases in the laboratories. In the latter case, we’re mainly talking about the gas plant and pipework,” says project leader Denis den Boer, who explains two specific solutions in more detail. “The laboratory has a very high heat load, which means it needs sufficient cooling all year round. As a thermal energy storage system proved uneconomic, a combination of two- and four-pipe air-to-water heat pumps was chosen. This allows the heat that needs to be removed to be used for heating the offices, among other spaces.” The high air-change rates in the laboratories also mean that humidification is required. “That’s why we opted for energy-efficient adiabatic humidification, to ensure a comfortable indoor climate throughout.”

Safety first
With a lead time of less than a year, Van Dorp Projecten decided to deliver as many installation components as possible to the project site prefabricated. These included the large heating and chilled-water units in the plant room, as well as the drainage and rainwater discharge components. The decision will save a considerable amount of time during installation, but it also brings new challenges. “You have to adjust your schedule, get the logistics in order and make sure you have enough storage space,” says Den Boer. “At the same time, safety must be guaranteed to the fullest extent. Following our client Burgland Bouw, we hope to achieve level 3 of the Safety Culture Ladder in the final quarter of 2025. That entails serious responsibilities. You have to keep safety front of mind and make continuous improvements wherever possible. For us, ‘unsafe means no work’. That motto applies in Amersfoort too.”

Tackling clashes
Van Dorp Projecten generally draws its installation designs in 3D using Revit. In Amersfoort, however, a different solution was needed, partly because of the short lead time. “In the end, we decided to put the entire BIM model in Autodesk Construction Cloud (ACC),” says Den Boer. “This means all project partners can work in the same model, allowing any clashes to be identified and resolved early. It also provides an excellent basis for prefabricating the required installation components in the traditional way.”