75 individual heat pumps for new residential building in Cuijk

A new residential building with 75 rental apartments has recently been completed on Irenestraat in Cuijk. After close consultation with Panasonic Heating & Cooling Solutions, AGO Technische Installaties chose to equip the gas-free complex with 75 individual systems rather than the collective system originally envisaged. William van Driel, Key Account Manager, air-to-water heat pumps, explains the rationale behind this choice.
“We’ve been extracting energy from the air for more than sixty years,” says Van Driel. “Here in Cuijk, we’ve shown that an individual configuration is a more attractive alternative to a collective system. First of all on cost, but certainly also when it comes to servicing and maintenance. Another benefit is the energy saving achieved. For example, there is no need to install a recirculation pipe for domestic hot water, and there are no pump losses. In addition, all the outdoor units are installed on vibration-free mounting rails on the roof.”

All-in-one
Each apartment has its own all-in-one indoor unit, including a 185-litre cylinder and condenser. The unit is 1.80 metres high and has a footprint of 60 by 70 centimetres. “So it takes up relatively little space. That’s also helpful, as it maximises the floor area available to rent,” Van Driel points out. Each indoor unit has its own 5 kW outdoor unit, which still delivers 4.2 kW at -10ºC, enough to heat the apartments. “With a little careful planning, it was easy to route the pipework between the indoor and outdoor units. The difference in height is no problem. Our units can easily bridge a height difference of 20 metres. The entire roof is filled with rows of five units, grouped by shaft. They are connected to the heat pumps from the ground floor up to the fourth floor, with enough space between them to prevent them from affecting one another.”

TOjuli
There is no room left on the roof for PV panels. According to Van Driel, that is not necessary either. “Thanks to an equivalence statement for our units, an individual system performed better in the EPC calculation, even without PV panels. This means that no default value needs to be used in the EPC calculation for domestic hot water. The same applies if we were to assess the building under NTA 8800. The TOjuli requirement is offset by the cooling capacity of the individual systems. We are also currently working on a similar project that does include Panasonic PV panels. We can accommodate those too and create enough space for the outdoor units.”

In the cloud
For this project, Panasonic not only assisted with commissioning, but also provided input during the design process, particularly on the positioning of the units. “We routinely offer this option to installers. Not all roofs are as flat as this one,” Van Driel acknowledges. “We can also carry out the noise calculations. Despite the 75 outdoor units, no additional measures were needed, such as acoustic enclosures. All the systems in Cuijk will communicate via the cloud. AGO Technische Installaties can then monitor them remotely and change settings where necessary, if the residents give their consent. Should a fault occur, the installer can resolve it remotely. If that is not possible, the installer will at least know immediately which parts to bring.”