‘Brocacef’s temperature and humidity are monitored and controlled 24/7’

Pharmaceutical wholesaler Brocacef has recently expanded the Brocacef Science Park on the Park Forum business park in Eindhoven with an 8,500-square-metre distribution centre and offices. As with the new-build project in 2014, Heembouw carried out the design and construction work. Van den Pol Elektrotechniek was responsible for the electrical installation, while Vink Installatie Groep handled the building services installations. To automate the climate control systems, the installer from Roelofarendsveen called on A&S System Integrators from Uden.
“Two air-to-water heat pumps have been installed to generate heating and cooling,” says Jim Sour, Managing Director of A&S System Integrators. “The heat pumps are connected to a 4-pipe distribution system, allowing heating and cooling to take place simultaneously. Induction units combined with underfloor heating and cooling were selected as the heat-emission system for the offices. An air handling unit supplies sufficient fresh air, while five separate air handling units provide heating, cooling and ventilation for the distribution centre.”

The central control panel houses the freely programmable BRControls BRC-46 central primary system controller (see photo) and RIO I/O modules, which control and monitor the heating, cooling and ventilation systems.
Optimal preservation of medicines and medical products
To guarantee the quality and shelf life of the medicines and medical products in the distribution centre, strict requirements were set for temperature and humidity, which must remain within specified limits. “To ensure optimal preservation, all rooms in the new building are monitored and controlled 24/7,” says Sour. “This is done using BRControls automation solutions, with which we have enjoyed working for many years. BRControls products stand out for their high quality, reliability and long service life. The control technology has also been installed in the existing building (phase 1), dating from 2014.”

Separate control panels with RIO-MU22 Multi Remote I/O modules have been integrated into the air handling units in the distribution centre, significantly reducing the amount of cabling required.
Latest system controllers
For this project, A&S System Integrators took care of everything for installer Vink Installatie Groep. This included supplying and installing the switchgear and control panels, hardware and software products, and field equipment, as well as the control system cabling, says Sour. The new building uses BRControls’ latest system controllers, which communicate seamlessly with their predecessors, ensuring optimal compatibility. A central control panel has been installed in the plant room. “In this panel, we installed the freely programmable BRControls BRC-46 central primary system controller and RIO I/O modules to control and monitor the heating, cooling and ventilation systems. Separate control panels with RIO-MU22 Multi Remote I/O modules have been integrated into the air handling units in the distribution centre, significantly reducing the amount of cabling required. The offices’ room controls use the flexible IP BRN20 range, combined with BRT24 full-touch room controllers. Our installers laid network cabling between the new and existing buildings, after which the building automation systems could be connected as one integrated installation.”
The new Brocacef building was completed earlier this year.
Question about this story? Ask your question
Who worked on it
Brocacef Science Park in Eindhoven
- electrical engineeringVan den Pol Elektrotechniek
- mechanical installationsVink Installatie Groep
- automatiseringsoplossingenBRControls
Keep following this
Get an email when a new story is published. No account needed.
- ProjectBrocacef Science Park
- ThemeHealthy indoor air
- SubjectHVAC
- CompanyVan den Pol Elektrotechniek
- CompanyVink Installatie Groep
- CompanyBRControls