Energy-efficient heat pump installation for Wassink Installatie’s new premises

In summer 2019, Wassink Installatie moved into a former printing works on Snelliusstraat in Winterswijk, with around 700 m² of office space and 600 m² of warehouse space. Extensive renovation work was needed to adapt the building for its new use. As well as reconfiguring and structurally renovating the existing spaces, all the electrical and mechanical services were replaced.
Although this is (still) not standard practice for existing commercial buildings with offices, Wassink Installatie wanted to create an all-electric building in which the latest technologies were optimally integrated and coordinated. The premises on Snelliusstraat have therefore become a literal showcase for the company’s knowledge, expertise and commitment to sustainability. The entire roof is fitted with PV panels, and LED lighting has been installed throughout the building. All the glazing has also been replaced with high-performance glass, not only reducing heat loss and heat gain but also allowing for a smaller climate control system. Two air-to-water heat pumps in a master-slave configuration provide heating and cooling. A 4-pipe heat pump was chosen, allowing heating and cooling to take place simultaneously. At peak times, when the workshop and warehouse also need heating and more heating capacity is required, a reversible heat pump (slave) comes on line.

A notable feature of the system is that any surplus heat or cooling is not wasted outdoors, but is sustainably captured in the designated buffer tanks.
Both heat pumps were engineered and supplied by Lennox Benelux BV. The global manufacturer and supplier of refrigeration and HVAC products has had a very good relationship with Wassink Installatie for many years. “We regularly supply chillers and heat pumps,” says Martijn van Gijssel, Account Manager for the North East Netherlands at Lennox Benelux BV. “Being involved in the renovation of Wassink Installatie’s new, own premises in Winterswijk is a great compliment to our efforts.”
Optimal comfort, minimal energy consumption
In existing Dutch commercial buildings, the average number of heating hours (around 2,500) is considerably higher than the number of cooling hours (1,000 to 1,200), Van Gijssel explains. “That is why heating capacity often determines the sizing of the heat pump. However, using a single 4-pipe heat pump for heating and cooling can leave businesses with a huge surplus of cooling in summer. In Wassink Installatie’s case, we therefore decided on a different approach. The building is so well insulated that the number of heating hours has been significantly reduced. However, because heat is retained more effectively, the number of cooling hours has increased. We used those cooling hours as the starting point for the engineering design.” A smaller 4-pipe unit (AQUA4 AAH071) was selected to meet the full cooling demand, he says. “We then calculated how much heating capacity this system could provide. The shortfall is made up by a small reversible heat pump (ECOLEAN EAR 1003). It is a highly cost-effective solution that also qualified for an ISDE grant.”
The heating system in this project had to meet 100% of demand, even at low outdoor temperatures, Van Gijssel says. “We therefore based the transmission and heat loss calculations on an outdoor air temperature of -10°C, when the heat demand is highest. To avoid oversizing, the temperature in the warehouse was deliberately set lower.”

Two air-to-water heat pumps in a master-slave configuration provide heating and cooling.
At an outdoor temperature of 35°C, the 4-pipe unit can deliver up to 74kW of cooling. Its heating capacity at -10°C is 35kW. “When operating simultaneously, the heat extracted from certain areas of the building can be used to heat others. In this mode, the master unit can deliver as much as 95kW (!) of heat alongside its 74kW cooling capacity.” The slave unit has a heating capacity of 62.5kW (at -10°C) and a cooling capacity of 86kW (at 35°C).
Not a cooling load, but an additional heat source
“A notable feature of our system is that any surplus heat or cooling is not wasted outdoors, but is sustainably captured in the designated buffer tanks,” says Vincent Dahlhaus, Technical Director at Wassink Installatie. “This means we always have more than enough hot and cold water available whenever the heat pumps are running. In winter, the surplus cooling is used, among other things, to cool the server room ‘for free’.” Van Gijssel adds: “The heat extracted from the server room is also used to heat other areas. This means the server room is not an internal cooling load, but an additional heat source.”
Een zakelijke vraag aan Lennox Benelux B.V.? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeGas-free heating and cooling
- SubjectHVAC
- CompanyLennox Benelux B.V.