HVAC

Groothuisbouw factory hall renovation with high-performance underfloor heating

Groothuisbouw factory hall renovation with high-performance underfloor heating

A factory hall is being renovated on behalf of Groothuisbouw for the production of precast concrete walls. The hall is being heated with TECEfloor high-performance underfloor heating, using the new 5-layer Silver Line Quality PE-RT pipe. In addition, heat released by the drying tables is being used to create a comfortable working environment.

Dries uit de Fles, process engineer at Groothuisbouw: “Our success in the construction of prefabricated villas, we are currently building around 225 villas a year, means that we need to keep expanding our production facilities. This year, we are doing so with a new factory hall in Kampen. Underfloor heating is the most sustainable and effective way to heat this hall. The heat is, of course, supplied by a heat pump. The heat pump supplies the underfloor heating system and several boilers, with a combined capacity of 4,000 litres, which provide additional heating. The 4,000 litres of hot water must be available continuously for the curing process. A burst of heat is needed after the precast walls are poured to speed up curing on the drying tables. The heat released during this process is enough to create a comfortable working environment. At weekends, the underfloor heating maintains the required indoor climate. Every day, heat that collects at the top of the hall will be circulated into a nearby hall by fans rather than vented outside. This allows us to use the heat effectively and avoid wasting energy.”

As well as residential construction, TECE specialises in underfloor heating for applications such as factory halls, commercial buildings, logistics centres, hangars and garden centres. Examples include the recently completed Overvecht garden centre in Tilburg and the EliteJet headquarters with two adjoining aircraft hangars. Like this project, both were installed by Montagebedrijf Azer. Jerome Azer: “We work with TECE on installations, but we also carry out our own projects, such as the garden centre in Tilburg. For this factory hall, we installed around 1,150 m² of underfloor heating, with 67 circuits at 15 cm centres. A total of 8,600 m of the new 5-layer Silver Line Quality PE-RT pipe was used. Thanks to its five-layer technology, it is particularly suitable for demanding installation conditions. We also installed new modular plastic industrial manifolds, suitable for both heating and cooling. Each manifold has no fewer than 25 circuits, each with a maximum length of 200 m. Their modular design makes them easy to install and means that one or more circuits can be added at any time.”

Question about this story? Ask your question

Who worked on it

Groothuisbouw industrial building Kampen in Kampen, renovatie

  1. MontagebedrijfMontagebedrijf Azer
  2. underfloor heatingTECE

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectGroothuisbouw industrial building Kampen
  • ThemeGas-free heating and cooling
  • SubjectHVAC
  • CompanyMontagebedrijf Azer
  • CompanyTECE
Share this article

Follow Installatie & Bouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.