HVAC

Precisely controlled indoor climate for WDP fulfilment centre in Nieuwegein

Zowel voor de bestaande bouw als voor de nieuwbouw heeft Western Airconditioning zes dakcentrales geleverd, die verschillen in luchthoeveelheid (5.100 m³/h tot 53.000 m³/h) en koelcapaciteit (20 tot bijna 300 kW).
Zowel voor de bestaande bouw als voor de nieuwbouw heeft Western Airconditioning zes dakcentrales geleverd, die verschillen in luchthoeveelheid (5.100 m³/h tot 53.000 m³/h) en koelcapaciteit (20 tot bijna 300 kW).

The refurbishment of WDP Nederland N.V.’s distribution centre in Nieuwegein, alongside the A27, was completed on 13 August 2020. Commissioned by WDP, the existing building has been transformed into a fulfilment centre for an online supplier. Work is also nearing completion on an adjacent new-build facility, bringing the total net floor area to 83,000 m².

“A number of modifications have been made to the existing building, which dates from 2011. In addition, the building services have been renewed to meet today’s climate requirements,” says Ben van Ooijen, Director and Project Manager at Mekann Projectmanagement & Advies. Mekann produced the concept design for the installations and defined the climate requirements in a specification. “We were also involved in selecting the contractors. Based on factors including quality and sustainability, the building services contracts were awarded to mechanical and electrical contractor Hoppenbrouwers Techniek, Heesch branch. For advice, engineering and the supply of the rooftop units, chiller and dry coolers, we approached Western Airconditioning, whose systems also stand out for their high energy efficiency.”

The two dry coolers connected to the aquifer thermal energy storage (ATES) system serving the existing building.

Stringent requirements

“This project is subject to fairly stringent requirements, which are also covered by a guarantee,” says Van Ooijen. “These include requirements for heating and cooling capacity. It was therefore crucial to select the right systems and suppliers. Taking into account factors such as the size of both buildings, the processes carried out inside them, the heat generated and the impact of the weather, we proposed using rooftop units capable of heating, cooling or cooling only.”

Independent rooftop units

“Working with Mekann, we assessed various installation options and determined the right capacities,” says François van Gorkom, Account Manager at Western Airconditioning. “Based on cost and efficiency, we opted for independent rooftop units for each space. We supplied six rooftop units for both the existing and the new buildings, with airflow rates ranging from 5,100 m³/h to 53,000 m³/h and cooling capacities from 20 to almost 300 kW. Together, the units have a total airflow of 410,000 m³/h and cooling capacity of 2.2 MW. With the components correctly matched, they achieve an average seasonal energy efficiency ratio (SEER) of 3.7 in cooling mode.”

Heat pump configuration

In addition to the rooftop units, Western Airconditioning supplied a chiller with a cooling capacity of 280 kW to provide underfloor cooling in the existing halls. “We also supplied two 150 kW dry coolers for the existing building. These are connected to its ATES system.” The aim was to condition the offices in the existing building using free cooling (outside air) as far as possible, says Van Ooijen. “In summer, cooling is provided by the ATES system. When it cannot meet demand, an existing heat pump provides mechanical cooling. We connected two Western Airconditioning dry coolers to this system, minimising the use of mechanical cooling. This can significantly reduce energy consumption.” Van Gorkom adds: “As part of the heating system was already in place in the existing building, one rooftop unit was configured as a heat pump, so it can provide both heating and cooling. All six rooftop units for the new building were configured as heat pumps.”

In addition to the rooftop units, Western Airconditioning supplied a chiller with a cooling capacity of 280 kW to provide underfloor cooling in the existing halls.

Close collaboration

Western Airconditioning delivered the twelve rooftop units, chiller and two dry coolers to the project just in time, following the installation sequence set by Hoppenbrouwers Techniek. “The units for the existing building were lifted from the lorries onto the roof by crane and placed on the steel support structure, all in a single day,” says Frank van Hommel, W Project Manager at Hoppenbrouwers Techniek. “We then completed all the connections, after which we commissioned the system together with Western Airconditioning. All the rooftop units for the new building were delivered in mid-October. Commissioning will follow shortly.” Van Hommel is very pleased with the collaboration with Western Airconditioning. “The account manager and service engineers are highly involved, and communication is direct. This means we can respond quickly and work towards final handover in a focused way.”

Project details

Client  WDP Nederland N.V.
Building contractor Willy Naessens Industriebouw
Building services consultant Mekann Projectmanagement & Advies, mechanical and electrical installations, Hoppenbrouwers Techniek, Heesch branch
Rooftop units, chiller and dry coolers Western Airconditioning

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeHealthy indoor air
  • SubjectHVAC
Share this article

Follow Installatie & Bouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.