Rijksmuseum van Oudheden (RMO) is the national archaeological museum of the Netherlands. It is housed in an old town house and beguinage, a listed building complex owned by the State (Rijksvastgoedbedrijf) and part of Leiden’s protected townscape. Its collection comprises around 180,000 objects from the ancient civilisations of Egypt, the Classical world and the ancient Near East, as well as from the Netherlands in prehistoric, Roman and medieval times. Maintaining a stable indoor climate is essential to keeping the collection in optimum condition. Western Airconditioning’s air-to-water heat pump makes an important contribution to this.
Technisch Installatiebureau Nederland (TIBN) is responsible for maintaining the electrical and mechanical services at Rijksmuseum van Oudheden. When the museum’s chiller reached the end of its technical life last summer, the building services contractor from Maarsbergen contacted Western Airconditioning. “At TIBN’s request, we supplied and installed an air-to-water heat pump with a cooling capacity of 185.3 kW and a heating capacity of 190.8 kW,” says Hans van Nes, Account Manager at Western Airconditioning. “Heat pumps and chillers are usually installed outdoors, but for this project an indoor installation in the plant room was necessary, partly because the museum is a listed building. Our BETA REV RFE HP 18.4 was the perfect solution.”

Delivered in sections
According to Van Nes, Western Airconditioning and TIBN faced an interesting challenge. “The plant room on the museum’s seventh floor is fully enclosed by steel and can only be accessed through several doors, each at a different level. The heat pump unit could only be brought inside by fully dismantling it at our premises in Hoevelaken and transporting it to the museum in manageable sections.”
Assembled from the base frame upwards
Even then, getting the Western air-to-water heat pump inside proved to be a major undertaking. Getting the very heavy and fragile condenser over the threshold was particularly nerve-racking, says Van Nes. “The condenser, measuring as much as 5.2 x 2.1 metres, was eventually placed on a base frame in the plant room and assembled there. After extensive brazing and refrigeration installation work, the unit was charged with the correct refrigerant and connected to the existing heat distribution systems. All the work carried out complies with the latest requirements, including the Pressure Equipment Directive 2014/68/EC.”

Tailored maintenance contract
“Our service engineers are highly skilled and hold all the qualifications and certificates required to assemble and/or maintain air-conditioning and heat pump systems,” Van Nes emphasises. “The unit for RMO was ultimately delivered in compliance with the F-gas Regulation No 517/2014, complete with the refrigeration installation nameplate and equipment register/logbook, to the great satisfaction of all parties involved.” Western Airconditioning offers a comprehensive range of maintenance contracts for both Western equipment and other makes. “Here too, we have a contract tailored to this particular type of installation and its intended use.”
Question about this story? Ask your question
Who worked on it
Rijksmuseum van Oudheden in Leiden
- full-service installerTechnisch Installatiebureau Nederland (TIBN)
- air-to-water heat pumpWestern Airconditioning
Keep following this
Get an email when a new story is published. No account needed.
- ProjectRijksmuseum van Oudheden
- ThemeGas-free heating and cooling
- SubjectHVAC
- CompanyTechnisch Installatiebureau Nederland (TIBN)
- CompanyWestern Airconditioning