Work is nearing completion on the new distribution centre for Allround Cargo Handling (ACH) at Nieuw-Reijerwaard business park in Ridderkerk. The company specialises in the storage and logistics of goods for the food and chemical industries.
The new building will cover approximately 22,600 m2, including a mezzanine of approximately 3,500 m2 and approximately 830 m2 of office space. Once completed, it must operate entirely without gas, sustainably and energy-efficiently. BREEAM-NL ‘Very Good’ certification criteria are central to both the design and construction. Terberg Totaal Installaties’ building services make a significant contribution to this.

Commissioned by, and working closely with, main contractor Aan de Stegge Twello, Terberg Totaal Installaties is installing both the mechanical and electrical systems in the distribution centre. To ensure a smooth project timeline, the building services were first modelled in Revit and thoroughly clash-detected with all parties involved, minimising clashes and rework costs. “Installation work began in early January,” says Xander Bennebroek, Mechanical Project Manager at Terberg Totaal Installaties. “Where most distribution centres opt for air heaters/gas heaters, this project uses high-performance heat pump technology. Six air-to-water heat pumps on the roof will provide heating for the five distribution halls and the dispatch corridor. The offices will have Variable Refrigerant Flow (VRF) systems, which can provide heating and cooling simultaneously and efficiently. These areas also have underfloor heating along the perimeter, efficiently counteracting downdraughts from the façade.” In line with BREEAM-NL requirements, the temperature in the offices can be controlled in each 40 m2 zone, Bennebroek explains. “Ventilation is fully demand-controlled, based on CO2 concentrations. Each office section (A and B) will have its own air handling unit. Carefully optimised spacing between the ventilation extract and supply points (dilution factor) ensures optimum supply air quality.”
BREEAM-NL points
A large 1,750 kVA transformer station has been installed outside the new building. The building will be connected from here using conventional cabling, says Michel den Hollander, Electrical Project Manager at Terberg Totaal Installaties. “A comprehensive 2.4 MW PV system will be installed on the roof, feeding surplus energy back into the electricity grid in summer. Alongside this PV system, the energy-efficient LED lighting inside and outside the building will earn valuable BREEAM-NL points.” Like the ventilation systems, the office lighting will be switchable in 40 m2 zones, he says. “Daylight and motion sensors will also ensure that no energy is used unnecessarily. To monitor the consumption of the other systems too, all major energy consumers have been fitted with sub-meters. These include, for example, the refrigeration systems for the temperature-controlled warehouses, which are being installed by another contractor.”
Tight schedule
In addition to the systems mentioned above, Terberg Totaal Installaties is responsible for installing the cabling for the data network, access control systems and intruder alarm. On the mechanical side, the full-service contractor, with branches in IJsselstein and Capelle aan den IJssel, is also carrying out the plumbing and sanitary installations. The work is due to be completed just before the summer. To meet the tight schedule, installation work is being carried out in parallel wherever possible. Regular planning and coordination meetings are also held with the main contractor and all subcontractors, ensuring that speed, efficiency, quality and enjoyment of the construction process go hand in hand.
Project information
Developer
NXR Vastgoed B.V.
Architect
Architecten_Lab
Engineering firm
JVZ Ingenieurs
Contractor
Aan de Stegge Twello
Building services
Terberg Totaal Installaties
Ventilation systems
Van Kessel Ventilatie B.V.
PV system
Sunrock
Question about this story? Ask your question
Who worked on it
Distributiecentrum Allround Cargo Handling Ridderkerk in Ridderkerk
- developerNXR Vastgoed B.V.
- architectArchitecten_Lab
- engineering consultancyJVZ Ingenieurs
- contractorAan de Stegge Twello
- building servicesTerberg Totaal Installaties
- ventilation systemsVan Kessel Ventilatie B.V.
- PV-installatieSunrock
Keep following this
Get an email when a new story is published. No account needed.
- ProjectDistributiecentrum Allround Cargo Handling Ridderkerk
- ThemeGas-free heating and cooling
- SubjectBuilding services engineering
- CompanyNXR Vastgoed B.V.
- CompanyArchitecten_Lab
- CompanyJVZ Ingenieurs
- CompanyAan de Stegge Twello
- CompanyTerberg Totaal Installaties