Hotel Okura, Amsterdam | Reliable and compact power distribution systems provide Hotel Okura Amsterdam with optimal security

To provide the best possible service to its hotel guests and maintain the quality of its service and provision at the highest possible level, Hotel Okura Amsterdam recently added a 1,700 kVA standby generator to its electrical installation. SDR Elektrotechniek was responsible for delivering this standby power installation. For power distribution to the main switchboard, the hotel’s electrical contractor called on Amsterdam-based Busbar Systems, which designed, supplied and installed several busbar systems.
“Because of the complex route between the generator connection cabinets (GAK) and the main switchboard, with numerous obstacles, steps, right-angle bends and narrow passages, cabling was not advisable for this project,” says Dennis te Winkel, Project Manager and Engineer at Busbar Systems. “Instead, we opted for our busbar systems, which are not only very compact, but can also be installed neatly, including around right-angle bends. Outside the hotel, we installed our EAE CRA IP68 (cast-resin) systems, which are highly resistant to weather, wind, water and changing (extreme) temperatures. Inside the building, we chose our modular EAE KXA IP55 systems, which can be connected directly to the IP68 systems.”

Because of the complex route between the generator connection cabinets (GAK) and the main switchboard, cabling was not advisable for this project. Instead, busbar systems were chosen, as they are not only very compact, but can also be installed neatly, including around right-angle bends.
In addition to the standby power installation, the five-star superior hotel had more than 800 solar panels installed on its roof, for which Busbar Systems also designed and installed the busbar systems. “The right-angle bends and compactness of our systems also played a key role on this project,” says Patrick Visser, who was hired by Busbar Systems as Lead Installer for the work. “By opting for busbar systems, SDR Elektrotechniek was able to outsource the entire power distribution to us. Busbar systems also result in low voltage losses, which is crucial for solar installations.” The same systems were used for the solar installation as for the standby power installation, he says, but with a capacity of 800 amperes. Busbar Systems completed the work in early July.
Question about this story? Ask your question
Who worked on it
Hotel Okura Amsterdam in Amsterdam
- in-house installerSDR Elektrotechniek
- Busbar SystemenBusbar Systems
Keep following this
Get an email when a new story is published. No account needed.
- ProjectHotel Okura Amsterdam
- ThemeBuilding electrical systems
- SubjectBuilding services engineering
- CompanySDR Elektrotechniek
- CompanyBusbar Systems