IJsselland Hospital | Capelle aan den IJssel

Routine maintenance keeps IJsselland Hospital switchgear in top condition
Last November, maintenance was carried out on the ACB switchgear at IJsselland Hospital in Capelle aan den IJssel. In accordance with the specifications of supplier Hager, all the hospital’s air circuit breakers were isolated, withdrawn from the switchgear, thoroughly inspected, serviced and tested, ensuring the correct operation, safety and reliability of the switchgear for years to come.

The air circuit breaker is checked both mechanically and electrically.
The switchgear at IJsselland Hospital dates from 2013. The installation comprises two 1,600-amp main switchboards, each containing six air circuit breakers and two spare switches, explains Conno van der Heiden, inspector and owner of CH Inspecties and delegated electrical installation responsible person at IJsselland Hospital. All the building services installations are supplied from the main switchboards, from the lighting and power systems to the climate control and medical installations. “At the request of IJsselland’s installation responsible person, Jan de Boer, I recently drew up an operating procedure for the hospital’s electrical installations, based on NEN 3140. A Risk Inventory and Evaluation (RI&E) was then carried out. This led to an inspection and maintenance schedule, which showed that the main switchboards were due for inspection and maintenance. To ensure the work was carried out to the highest standard, I contacted supplier Hager on behalf of IJsselland Hospital. Hager has the right expertise, certifications and any replacement parts that might be needed.”
Thorough preparation and execution
“Conno and I mapped out the work and possible times for carrying it out,” says Martwin de Man, Service Manager at Hager. “We then identified the tools and personnel required, along with the safety considerations and any potential risks, and drew up a work plan on that basis.” Van der Heiden adds: “The spare switches were serviced in the week before the work began. The remaining air circuit breakers were then thoroughly inspected, serviced and tested on 24 November.”
“Before starting work, we held an introductory meeting, including a safety briefing for everyone involved,” says De Man. “We discussed the work plan, prepared the work area and carried out a Last Minute Risk Analysis. Once Conno had carried out all the switching operations for the hospital, we removed the air circuit breakers from the switchboards.” The maintenance began with an inspection of the mechanisms, arc chutes and switching contacts, he explains. “We then carried out the mechanical maintenance, lubricating and testing the gears, springs and coils, among other things. Finally, we checked the protection relays and their settings. These trip the air circuit breaker in the event of an overload or short circuit. All our findings and recommendations were summarised in a report.”
Uninterrupted power supply and safe maintenance

Conno van der Heiden (centre) and Martwin de Man (second from right) with the maintenance team.
One requirement during the maintenance was that all installations at IJsselland Hospital remain energised. “The work was carried out on a Saturday, when the outpatient clinics are closed and staffing levels are at a minimum,” says Van der Heiden. “Demand is also lower in the winter months, as less cooling is needed.” De Man adds: “Each of the main switchboards at IJsselland Hospital is supplied by a single transformer. If the power fails, an emergency generator starts up. However, the main switchboards are configured so that they can also be supplied by one transformer and one emergency generator through switching operations. Provided, of course, that the demand allows it. This meant we could isolate one air circuit breaker at a time and swap it for a spare switch. That allowed us to carry out maintenance safely without putting the hospital’s power supply at risk.”
Several months after the work, Van der Heiden looks back on a pleasant and trouble-free project. “Thorough preparation and open communication certainly contributed to that. Between 2013 and 2018, we carried out quite a few switching operations at the hospital to gain a clear picture of the installation. Despite this, the main switchboards were still in excellent condition.” De Man agrees. “We found no major defects during the maintenance. We are therefore confident that, with this management and regular maintenance, our switchgear can continue to operate trouble-free for many years.”
A business enquiry for Hager? Get in touch
Wie aan IJsselland Ziekenhuis werkte
- inspecteurCH InspectiesIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectIJsselland Ziekenhuis
- SubjectBuilding services engineering
- CompanyHager
- CompanyCH Inspecties