Dutch family business Nijburg Industry Group produces, supplies and installs complete solutions for a healthy indoor climate. For a large distribution centre currently under construction, the company is supplying and installing all the ductwork, fittings (fire dampers, damper assemblies and VAV/CAV) and grilles.

Nijburg Industry Group comprises several divisions: Sales, Installation and Production. For this project, the Installation division worked with Barth Installatietechniek from ’s-Gravendeel, a long-standing partner of the company. Alex Walraven, director of the Installation division: “The distribution centre includes a warehouse, freezer rooms and offices, each with different systems. Air is supplied to and extracted from the warehouse, while dry air is supplied to the freezer rooms to prevent mould. We installed a system for cooling and heating in the office area. There is a heat recovery unit there, with ducts connected to it.”

Phased start

Nijburg began work in January 2021, when the weather in the Netherlands was very cold. A few weeks later, it even snowed. And the building was still open, Walraven explains. “The poor weather made for a difficult start to the project. Work began in phases, while the main contractor was still busy pile-driving. The roof was still open and the façade had not yet been installed. The building is in an exposed location, which made installing the ductwork difficult for us. The roof panels were already in place, but there was no roof covering. So we made sure our employees had the right clothing and could work at height using mobile elevating work platforms and other equipment.”

The installation work was carried out from a walkable ceiling. The hall is 20 metres high, and the ceiling was at a height of 14.60 metres. “Fortunately, our materials can withstand some water, and we covered everything with tarpaulins during installation. We had to wait much longer to install the insulation,” says Walraven.

Cooperation with the client and the installer runs smoothly thanks to good consultation and communication.

Planning is key

Nijburg Industry Group often works for the client and for Barth Installatietechniek, but this project was quite different from the company’s usual work, says Walraven. “We often work on hospitals and offices. But whatever the project, planning is always especially important. We deliver large components, such as air ducts. They need to arrive at the right time and be installed quickly, otherwise they can disrupt the work of other contractors on site. That requires good coordination with the client and the installer.”

All’s well that ends well

Despite the difficult start caused by the poor weather, the team still looks back on a rewarding project. Bas Biezen, project manager at Nijburg Klimaattechniek: “Working with Barth Installatietechniek is always a pleasure. We are a true partner to this installer, and that feels good. We are brought into projects early to review the planning. We can discuss any bottlenecks with each other in good time.” Walraven adds: “Getting products to site at the right time is the most important thing on a project like this. We completed everything well within the schedule. It was a very tight schedule, but we got there in the end.”      

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeHealthy indoor air
  • SubjectBuilding services engineering
Share this article

Advertisement

Follow Installatie & Bouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.