Library becomes Faculty of Law
Text Desiree PenningsImage Homij

A year ago, the former Groningen library reopened, this time as the home of the Faculty of Law at the University of Groningen and under the name Rölinggebouw. An extra floor was added to the building, along with a new courtyard and a second entrance. Homij delivered the complete mechanical and electrical installations.
First, the former library was completely stripped out before being given a new layout. The building was originally designed by Italian architect Giorhio Grassi. He also played a role in the renovation, helping to preserve the existing style. Grassi had designed the extra floor back then, and it has now become a reality.
As well as work, study and meeting spaces, the basement houses a moot court. This area is connected to the central reception space by tiered seating. Additional daylight was brought into the building to create a pleasant working and learning environment.

A tight site
Homij installed all the mechanical and electrical systems in collaboration with main contractor Visser & Smit Bouw, starting from scratch. Based on the university’s requirements, the installation was fully designed and implemented. Much of it was developed in advance in a 3D model, allowing components to be supplied as prefabricated units. Arend Riemersma, project manager at Homij: “We could deliver the installation ready to go and then assemble it. That meant fewer operations were needed on site.”
It was a city-centre project, so good schedules and agreements were needed to deliver the materials, Riemersma explains. “The construction site itself was postage-stamp sized, just a tiny inner courtyard. Inside the building, we created empty spaces where the staff could take their breaks.”

Headaches
That was not the only challenge Homij faced. Various surprises came to light during the renovation, and solutions had to be found. The existing structure in particular meant that it was not always possible to do everything the installers had planned. Riemersma: “In consultation with the structural engineer and architect, we looked for new solutions. The project was mainly about thinking smart: how can you install efficiently so that you can still fit everything in within a short time? We worked together to find solutions that would keep us within the schedule.”

Looking back
Work began in April 2022, and Homij completed it in 2023. New main and sub-distribution boards, sustainable LED lighting, a heat pump system, solar panels across the entire roof, climate controls with occupancy detection: everything was installed using Homij’s own plug & play DLS concept. One advantage was that the building consists of several identical wings, so the installers knew exactly what was expected of them. The company is also responsible for ongoing maintenance.
After handover, it was clear that the building had turned out beautifully, but of course the users also needed to be satisfied with the spaces and indoor climate. By September, they will have been using it for a year, and the installation is working entirely as intended. “We’ve had feedback that they’re really pleased with it. We worked hard to complete the project on schedule. We put a lot of energy into it, and we’re proud of what we’ve achieved,” says Riemersma.
Question about this story? Ask your question
Who worked on it
Rölinggebouw in Groningen
- contractorVisser & Smit Bouw
Keep following this
Get an email when a new story is published. No account needed.
- ProjectRölinggebouw
- SubjectBuilding services engineering
- CompanyVisser & Smit Bouw