Plug-and-play installations for St. Jans Gasthuis in Weert
Text Lieke BousemaImage Isolectra

At the end of November, St. Jans Gasthuis (SJG) in Weert will move into a new, modern and future-proof hospital building. The new building has been designed to meet the latest sustainability requirements. It can also adapt exceptionally well to both contraction and growth. Isolectra’s plug-and-play medical boxes are among the solutions making an important contribution to this.

Compact and easy to navigate
Designed by Wiegerinck Architecten, the new hospital has a floor area of 20,000 m2, making it much more compact and easier to navigate than the old building, which covered 35,000 m2. This has been made possible in part by using space more efficiently and streamlining work processes as much as possible. BAM Bouw en Techniek is delivering the entire new-build project, which consists of five floors. The ground floor will house the emergency department, GP out-of-hours service, intensive care unit, medical imaging department, pharmacy and blood-drawing laboratory, while the outpatient clinics will be on the first floor. The second floor will house a women’s, maternity and children’s centre and the day treatment unit, while the third and fourth floors will be used for inpatient wards. All the building services will be located on the fifth floor.

Installation up to 40% faster
Most of the electrical installations at St. Jans Gasthuis are plug-and-play, from standard power installations through to lighting and medical installations, says Peter Hollander, site manager at BAM Bouw & Techniek. “We made this choice deliberately, because it delivers significant efficiency gains and speeds up the work. The entire hospital has to be fitted out within a year. By opting for plug-and-play, we can install everything up to 40% faster. We can achieve a rate of around four rooms a day.”

A concept for plug-and-play medical installations
St. Jans Gasthuis is one of the first hospitals for which Isolectra has supplied the complete plug-and-play medical installation in-house, says Bran Jalink, innovation manager at Isolectra. “Medical installations are subject to a number of mandatory requirements. Earthing and equipotential bonding are a good example: they neutralise differences in voltage. This is an important consideration for patient and electrical safety. We have developed special MediBoxen to which all supplies for G0 and G1 rooms can be connected easily and safely. A copper support rail provides the required equipotential bonding.” Hollander adds: “The MediBoxen are installed above the suspended ceilings in patient and treatment rooms, in carefully selected positions above the beds and treatment areas. From there, we can easily plug in connections to the bedhead units, installations and earthing.”
For other hospitals too
“During the preparatory phase, we worked closely with BAM Bouw en Techniek on the plug-and-play concept for the medical installations,” says Jalink. “We also developed and drew up detailed plans for all the standard rooms for the contractor. We then fully prefabricated and extensively tested the plug-and-play MediBoxen, and held an on-site demonstration and toolbox meeting.” These efforts have resulted in a unique, universal plug-and-play concept for medical installations, which Isolectra can also use in other hospital projects. “The first projects using the concept are now in preparation.”
Now available for G2 rooms too
Isolectra supplied a total of 219 plug-and-play MediBoxen for St. Jans Gasthuis. “All the box outlets are clearly labelled and numbered. This means the boxes can be installed quickly and efficiently, without requiring specialist medical or technical knowledge. The maintenance engineer will also be able to see at a glance which connection serves which function.” The plug-and-play medical installation at St. Jans Gasthuis has been used in all rooms classified as G0 and G1, says Jalink. “We now also have solutions for G2 rooms, so even more hospital spaces can be fitted with plug-and-play installations. We are also unique in the market in using two 2.5 mm2 cables for medical equipotential bonding, rather than the usual 6 mm2 cables.”
Extension at the rear
The project is due to be completed around the time of the summer building holiday. Once the new building is complete, preparations will begin for an extension to the rear of the hospital, on Boerhaavestraat. This will provide space for the operating centre, several outpatient clinics, office space and the restaurant. Phase 2 is due for completion in 2030.
Have a business enquiry for Isolectra BV? Get in touch
Who worked on it
St. Jans Gasthuis in Weert
- stekerbare medische installaties
Isolectra - architectWiegerinck Architecten
- contractorBAM Bouw en Techniek
Keep following this
Get an email when a new story is published. No account needed.
- ProjectSt. Jans Gasthuis
- SubjectElectrical engineering
- CompanyIsolectra BV
- CompanyWiegerinck Architecten
- CompanyBAM Bouw en Techniek