Quality and efficiency come together in electrical installation at TU/e campus
Text and images Van Hees Elektrotechniek & ICT

Stichting Woonbedrijf SWS Hhvl, architect VenhoevenCS and Heijmans have delivered 735 student homes on the site of Eindhoven University of Technology, better known as TU Eindhoven. The scheme comprises an East and a West Tower, each with fourteen storeys. Between the residential towers is a low-rise building with two-storey group accommodation. It also houses the commercial units. The compact homes meet all the standards of modern living. They are all-electric and equipped with all the systems required by student life today.
Electrical installations
Van Hees installed virtually all the electrical systems for this project, from the site infrastructure to all the electrical services in the homes. These included the lighting installation, site cabling, data installation, control cabling for the solar shading, bus cabling, earthing system, sub-distribution boards, power cables and cable trays, intercom and evacuation systems. When the installer left the site, it was a fully operational building, ready for occupation and use.
Large-scale project
With 735 homes, this was undoubtedly a mega-project. For Van Hees, it is one of its largest projects. Preparing the project took more than a year. Once the tender phase had been completed and the contract awarded to Van Hees, work began on developing the drawings and carrying out the many other preparations required. Van Hees appointed the right subcontractors, assembled a team of skilled professionals, purchased the materials and organised the equipment. At the peak of the project, 22 Van Hees installers were on site. Coordinating all this was a challenge in itself.
Collaboration is crucial
Although Van Hees specialises in electrical installations, these systems are closely integrated with the building services installations on every project. This called for expert consultation and close collaboration. Drawing on its experience and working with the right people, Van Hees discussed all the interfaces and details. These were coordinated and incorporated into a 3D/BIM model. Despite the scale of the project, all the installations were built together, precisely to schedule. Van Hees looks back on excellent collaboration with all parties during the construction process.
Added value for the future
TU Eindhoven can offer its students comfortable accommodation on this modern university campus. The homes meet the latest sustainability standards. The project also added value for Van Hees. The company has gained considerable experience in delivering large-scale projects and is even more aware that it has seasoned professionals on board who work calmly and expertly, even when the pressure mounts. “We also know that we can rely on our trusted partners, who, like us, are committed to honouring the agreements we have made.”
Question about this story? Ask your question
Who worked on it
TU/e student accommodation in Eindhoven
- architectVenhoevenCS
- electrical installationsVan Hees Elektrotechniek & ICT
Keep following this
Get an email when a new story is published. No account needed.
- ProjectTU/e student accommodation
- ThemeBuilding electrical systems
- SubjectElectrical engineering
- CompanyVenhoevenCS
- CompanyVan Hees Elektrotechniek & ICT