Successful introduction to plug-in installation at Landgoed Mennorode
Text Lieke BousemaImage Ponsioen Installatie Techniek en Isolectra

Set amid the beautiful forests of the Veluwe, Landgoed Mennorode opened its Mennonite brotherhood house in 1925. It has since grown into a hotel and conference centre with no fewer than 172 hotel rooms and more than thirty function rooms. To make guests’ stays even more comfortable and create a unique experience, Mennorode is investing heavily in modernisation and sustainability, in keeping with the atmosphere and character of the estate.
The masterplan, ‘Mennorode, honderd jaar verder’, aims to future-proof the complex. The first of four implementation phases has recently been completed. This phase included the renovation of the façade, the refurbishment of 22 rooms and improved access. Together, these measures create cohesion, enhance the quality of guests’ stays and restore the connection with the surrounding landscape. Van Dillen Bouw was responsible for the building work, while Ponsioen Installatie Techniek carried out all the electrical and mechanical services work, with the aim of modernising the hotel and making it gas-free in the future.

New installation techniques
“The first phase was completed just before the 2025 builders’ holiday and involved a wing with two floors and 22 hotel rooms,” says Sander Goedhart, project manager at Ponsioen Installatie Techniek. “We installed new systems here, covering electrical, water and central heating, so that the system can later be connected to the new central heating and cooling plant with heat pumps. Replacing the high-temperature heating system with a low-temperature system can deliver substantial energy cost savings.” Given the repetitive nature of the work in the hotel rooms, plug-in technology was chosen for the electrical installations, he says. “From the power cables right through to the socket outlets, lighting and associated switches, this meant we could install much faster and without errors.”

Excellent support
“We had gained some experience with plug-in installation in the past,” says Goedhart. “As the collaboration had not always gone smoothly, we looked for an alternative supplier for the installation at Hotel & Conferentiecentrum Mennorode. We found one in Isolectra, the pioneer of plug-in installation in the Netherlands, with extensive knowledge and expertise. Our contact with account manager Saïd Omaaza and technical consultant Bran Jalink was very positive. We received excellent support during the quotation process, with the plug-in design for the hotel rooms and with deliveries.” As the project developed, the final lead time became extremely short, Omaaza explains. “That was no problem for Isolectra, because our systems are held in ample stock at the usual wholesalers.” Goedhart adds: “Most of the order for this project was supplied through wholesaler Rexel, with a small part managed in-house. Some installations could also be assembled specifically for the project.”
Completely taken care of
Hotel & Conferentiecentrum Mennorode was Ponsioen Installatie Techniek’s first experience with Isolectra’s Wieland systems. “That is why Isolectra took care of the engineering for the first phase in full and produced the design for us.” The first discussions took place in December 2024, says Omaaza. “Conventional installation drawings for the project had already been prepared by then. We converted these in-house into a plug-in concept, including a schedule of all the plug-in components required, quantities and cable lengths. This enabled Ponsioen Installatie Techniek to order exactly the right products.”
Joint project start
“At the start of the work, Bran Jalink supervised the plug-in installation in the first room and shared a few tips and tricks, which helped us install the remaining 21 rooms very efficiently,” says Goedhart. “So we didn’t have to reinvent the wheel.” Ponsioen Installatie Techniek intends to use Isolectra’s Wieland systems in the next phases too. “As the lead times for these phases are a little longer, we can benefit from another service offered by Isolectra, whereby all the systems are supplied to the project kitted for each room. This will enable us to install even faster.”
Have a business enquiry for Isolectra BV? Get in touch
Who worked on it
Hotel & Conferentiecentrum Mennorode
- Wieland-systemen
Isolectra - elektrotechnische en werktuigbouwkundige werkzaamhedenPonsioen Installatie Techniek
- construction workVan Dillen Bouw
- wholesaleRexel
Keep following this
Get an email when a new story is published. No account needed.
- ProjectHotel & Conferentiecentrum Mennorode
- ThemeBuilding electrical systems
- SubjectElectrical engineering
- CompanyIsolectra BV
- CompanyPonsioen Installatie Techniek
- CompanyVan Dillen Bouw
- CompanyRexel


















