High-efficiency chillers for new TKF facility in Eemshaven
Text Lieke BousemaImage Western Airconditioning B.V.

Production of inter-array subsea cables requires precise cooling
On 19 March, the new subsea cable factory for B.V. Twentsche Kabelfabriek (TKF) was structurally completed at Borkumkade in Eemshaven. The new subsea factory prepares TKF for the move towards higher power ratings for offshore wind turbines. The new factory will produce around 1,200 kilometres of inter-array subsea cables a year for TKF, connecting offshore wind turbines to the substation. Several production processes, including wire drawing and extrusion, require exceptionally precise cooling. Western Airconditioning B.V.'s air-to-water chillers play an important part in this.
The new subsea cable factory for TKF was built by the VOF Sub Sea construction consortium (Dura Vermeer Bouw Hengelo, Dura Vermeer Infra Oost and Aannemingsmaatschappij Friso). Expert firms Ebbens Engineering of Lochem and Western Airconditioning B.V. of Hoevelaken once again joined forces to design and install the hardware and controls for the cooling process. In 2018, the companies had already delivered a similar cooling solution for TKF's impressive production facility in Lochem. “As in Lochem, cooling in Eemshaven is achieved using cooling water, with the process controlled according to the production requirements,” says Arnoud Kerkhove, Account Manager at Western Airconditioning. “The production processes generate a great deal of heat, which is then removed using water supplied by our chillers.”

Redundant configuration
“The entire cooling system has a redundant configuration, with duplicate pumps for each chiller, including the necessary circulation pumps,” says Kerkhove. “Together with a full Master-Slave configuration, this ensures TKF has a high-quality, reliable cooling process.” If more cooling capacity is needed than one chiller can provide, the second chiller automatically switches on, he explains. “If one of the chillers should unexpectedly develop a fault, the other takes over the entire cooling process. We monitor both units in real time, 24/7, using the Western Airconditioning monitoring system.”
Full-inverter-driven screw compressors
This project uses two KAPPA SKY Xi 89.2 air-to-water chillers running on R134a refrigerant. The low-noise (LN) units are fitted with two Xi full-inverter-driven screw compressors, as they also operate at part load for much of the time, says Kerkhove. “This allows us to turn down the cooling capacity to 12.5%. With a compressor capacity of 950 kW per chiller, the total installed cooling capacity is as much as 1,900 kW. Each chiller also has two chilled-water pumps (N+1 configuration). The units are guaranteed to operate in outdoor temperatures ranging from -20 to +50 degrees Celsius, even during hot summers and cold winters.”
Closed system
The chillers are connected in a closed system to a plate heat exchanger, says Kerkhove. “The chillers are supplied with water from a buffer tank. This tank supplies all the points of use with water at a constant temperature of around 18 degrees Celsius. The water used flows back from the factory by gravity.”
Delivered just in time
The chillers were transported just in time from the factory to TKF's subsea cable factory. The units, weighing approximately 8 tonnes each, were lifted straight from the lorry into position. Ebbens Engineering connected the machines electrically and to the water circuit, after which a service engineer from Western Airconditioning B.V. fully commissioned and set up the chillers for the production process.