Moba Barneveld revitalisation:

‘Our work must not disrupt the factory processes’
It can hardly have escaped anyone’s notice: the renovation of Moba in Barneveld is proceeding at pace. In September 2018, the global market leader in egg grading and egg packaging machines began an extensive renovation and new-build project, which is being carried out in several phases.
The new industrial hall, with its technical services room, staff restaurant and meeting facilities (phase 1), and the new injection moulding hall, granulate storage facility, toolmaking workshop and mould store (phase 2) are now complete. The new office building (phase 3) is due for completion in early October. Work has also recently started on extending the façade line on the south-east side and landscaping the forecourt (phase 4).

In December 2017, a construction team was formed for the renovation and new-build project, comprising OPL architecten (Utrecht), Snetselaar Constructieve Ingenieurs (Ede), B&T bouwmanagement (Hardinxveld-Giessendam), construction company Hardeman (Lunteren), mechanical services contractor Wolf Klimaat Service (Baarn) and electrical contractor Leertouwer (Barneveld). “As a versatile and innovative systems integrator in electrical engineering, climate control systems and ICT, we are responsible for the design, engineering and installation of all electrical systems,” says Eric Versteeg, project manager at Leertouwer. “It is certainly no easy task, because Moba’s processes must not be disrupted while we are working. To make this possible, we installed two new transformer substations (2×1,000 kVA), connected to two new main distribution rooms. The entire factory is being reconfigured from these main distribution rooms inside the building, alongside the existing installation dating from 1960. Busbar trunking was chosen for energy distribution in the new injection moulding hall and toolmaking workshop, making it easy to transmit higher power loads. Traditional cabling has been used in the other areas.” The lighting in the factory halls is also noteworthy: it uses a 6500K colour temperature (daylight), says Versteeg. “The employees themselves selected this bright, lively colour of light after seeing a trial installation, because it clearly accentuates black-and-white contrasts and makes for a very pleasant working environment.”
In addition to the lighting and power installations, Leertouwer is also responsible for the data installation, fibre-optic network, fire alarm system and security system at Moba in Barneveld. “We have been Moba’s regular installation contractor for fifteen years, as has Wolf Klimaat Service,” Versteeg emphasises. “We know the factory and all its processes well, and know each other inside out. This keeps communication direct and allows us to work together very efficiently and enjoyably.”
Question about this story? Ask your question
Who worked on it
Moba Barneveld in Barneveld
- architectsOPL architecten
- construction companybouwbedrijf Hardeman
- Mechanical services contractorWolf Klimaat Service
- Electrical contractorLeertouwer
Keep following this
Get an email when a new story is published. No account needed.
- ProjectMoba Barneveld
- SubjectGeneral
- CompanyOPL architecten
- Companybouwbedrijf Hardeman
- CompanyWolf Klimaat Service
- CompanyLeertouwer