3,200-amp main switchboard powers new Grozette building

3,200-amp main switchboard powers new Grozette building

For almost 60 years, Grozette has processed cheese into fresh and dry grated cheese products for retail, foodservice and industry. The company has been based on Ohmweg in Woerden since 1973, where production capacity is currently being significantly expanded. Construction is divided into two phases. Phase 1 involves building on the land next to the existing premises and comprises office space and production areas, which were formally handed over last October. The existing building is now being demolished to make way for phase 2. The project is being built by Dijkham Bouw from Nijkerk. Lomans Amersfoort is responsible for the electrical and mechanical installations, except for the climate control systems in the new production hall. Sustainability and food safety are central to both the design and construction.

From office heating and cooling to sanitary installations, power supply, LED lighting, data installation, fire alarm system, intruder alarm, camera systems, access control and KNX/DALI building automation, Lomans Amersfoort has been involved in the new Grozette building since October 2020. Following phase 1, the full-service building services contractor will start work on the phase 2 installations in mid-March. “This energy-neutral project is being built to a BREEAM-NL ‘Outstanding’ ambition,” says Martin van de Kamp, project manager at Lomans Amersfoort. “For example, waste heat from the cold store refrigeration system is efficiently reused to heat the offices. Each toilet block will also have a solenoid valve in the water installation, linked to the lighting motion detector. Our social-return subsidiary Montage Jongens, which helps people who face barriers to employment find work in building services engineering, is installing more than 2,000 PV panels on the roof of phase 2.”

The 1,600-amp Engie switchboard is fed by the main switchboard and fitted with two H3+ MCCB circuit breakers.

Main and sub-distribution boards

Lomans Amersfoort is working closely with Hager on power distribution for the new building. “We were looking for a partner that could respond quickly, particularly when it came to the main switchboard,” says Van de Kamp. “Hager provided the best solution for our scheduling requirements. I also know Hager as a great company to work with. Communication was good on this project too. Using our drawings and details from our installation diagrams, including the number of circuits, the required rating of the main switch and the number of kWh meters, Hager handled the engineering for the main and sub-distribution boards. We then worked together on the detailed coordination, after which Hager began production.”

Abe de Jong, project manager at Hager: “For the new Grozette building, we designed, built and installed one large main switchboard, almost 10 metres long, with a 2 x 1,600-amp supply and a Combiway enclosure.” Combiway is a new type of enclosure from Hager, he explains, combining LL-series fuse-switch disconnectors and H3+ circuit breakers in a single compact outgoing cubicle. The enclosure also has space for Univers or DIN-rail components, making it particularly versatile. “The main switchboard will be supplied by two transformers. It is also ready for the PV panels to be connected, partly thanks to the installation of two busbar trunking connection points.”

For phase 1, 23 sub-distribution boards were supplied to power both the power installations and the lighting, says De Jong. A further 10 sub-distribution boards will be added in phase 2. All the sub-distribution boards are fitted with kWh meters for energy monitoring. “A notable feature of this project is the Engie switchboard for the refrigeration system in the production hall. This 1,600-amp switchboard is fed by the main switchboard and fitted with two H3+ MCCB circuit breakers for the standby generator and the bus-tie switch.”

Assembly of the main switchboard.

Just in time and in manageable sections

Hager assembled, tested and inspected the Engie switchboard and main switchboard in-house at its Coevorden facility. The boards were then transported to Woerden just in time and in manageable sections, and assembled on site, says De Jong. “Installing the Engie switchboard was particularly challenging because it had to go on the first floor. The height of the hall also meant the switchboard had to be lifted 6 metres inside the building. We worked closely with Kraanbedrijf Nederhoff to make this possible.” Hager again worked with its panel-building partner PS Nederland Noord B.V. on the sub-distribution boards. Lomans Amersfoort connected all the boards. Lomans Amersfoort and Hager jointly commissioned the main switchboard.

In addition to the main and sub-distribution boards, Hager also supplied plastic (tehalit) wall trunking for Grozette’s offices.

A business enquiry for Hager? Get in touch

Who worked on it

Grozette Woerden production expansion in Woerden

  1. Distribution boardsHager
  2. ClientGrozette BV
  3. ArchitectRDG Ontwerp & Advies
  4. ContractorDijkham Bouw
  5. Electrical and mechanical contractorLomans Amersfoort
  6. Refrigeration installerEngie
  7. panel building partnerPS Nederland Noord B.V.

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectGrozette Woerden production expansion
  • SubjectProjects
  • CompanyHager
  • CompanyGrozette BV
  • CompanyRDG Ontwerp & Advies
  • CompanyDijkham Bouw
  • CompanyLomans Amersfoort
Share this article

Follow Installatie & Bouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.