M&E systems form the basis for sustainable GLP DC in Venray

Brandsen Installatietechniek was responsible for almost all the mechanical and electrical installations at GLP’s sustainable, circularly built distribution centre in Venray. The turnkey installer from Barneveld once again demonstrated its extensive expertise in practice. Brandsen Installatietechniek director Berto van Vliet looks back with great satisfaction on the recently completed work, which was carried out by around 15 of the company’s own employees.
Completed at the end of August, the project is the second phase of GLP’s new distribution centre. The company is one of Europe’s leading investors and developers of logistics warehouses and distribution parks. The new DC on the Smakterheide industrial estate in Venray covers approximately 27,000 m2, providing ample space for a warehouse divided into two sections (including a mezzanine), several loading docks and a loading bay. The building also includes two office blocks, each spanning two storeys.
A varied M&E package
With the exception of the sprinkler and fire alarm systems, Brandsen, whose main areas of activity are new-build and renovation projects for homes and commercial buildings, installed all the M&E systems in the DC. “We fitted underfloor heating and cooling in the distribution centre and offices,” Van Vliet begins his list. “The office areas also have climate ceilings and ventilation systems. The same applies to the mezzanine, the self-supporting structure between the two floor levels. On the mechanical side, we carried out a good mix of traditional plumbing work, including drainage for both wastewater and rainwater, as well as the sanitary facilities. In short, we were able to demonstrate the full breadth of our extensive technical installation expertise.”

Propane as a refrigerant
The sustainable nature of the brand-new building on Smakterweg in Venray has earned it a BREEAM ‘Excellent’ design certificate. Alongside the installations already mentioned, another solution installed by Brandsen Installatietechniek makes a major contribution, as Van Vliet explains. “The building runs on two Emicon 4-pipe air-to-water heat pumps, type GPS/3402/Kp, designed for outdoor installation. These sophisticated units can be operated via remote monitoring, comply with the ATEX 114 guidelines and combine semi-hermetic piston compressors with low-noise fans, among other components. What makes these heat pumps particularly special, however, is that they use propane, or R290, as the refrigerant. Thanks to its favourable energy properties, this environmentally friendly alternative indirectly reduces CO2 emissions, thereby having a less harmful impact on the greenhouse effect.”
Safety first
In addition to their sustainable design, the heat pumps are exceptionally safe to operate. The compressors in both heat pumps are housed in an enclosed, sound-insulated casing fitted with a ventilation opening. A propane gas detection sensor is installed in the casing, with low (5% LEL) and high (10% LEL) alarm thresholds. “If propane is detected and the sensor’s low-level alarm contact is triggered, a fan in the compressor room will extract air from the space,” Van Vliet explains. “If the high-level alarm contact is triggered, the machine shuts down immediately. The fan continues to ventilate the space, however. Once the fault has been rectified, the machine can then be restarted manually.”
Question about this story? Ask your question
Who worked on it
Distributiecentrum GLP Venray in Venray
- full-service installerBrandsen Installatietechniek
- air-to-water heat pumpsEmicon