Neele-Vat opens sustainable new-build facility at Port Park Pernis

Neele-Vat opens sustainable new-build facility at Port Park Pernis

Family-owned logistics service provider Neele-Vat moved into a new, state-of-the-art distribution centre with its head office at the Port of Rotterdam in early September. The new headquarters, covering approximately 45,000 m2, has been built on the former Port Park Pernis site, close to the Eemhaven/Waalhaven container terminals and at the junction of the A15 and A4 motorways. Sustainability, energy efficiency and flexibility were key considerations during both the design and construction phases, including in relation to the mechanical and electrical installations.

Van Rennes installed the complete climate control system for Neele-Vat’s warehouse (approximately 38,000 m2) and office (approximately 7,000 m2).

Working for De Vries en Verburg Bouw as part of a construction team, Van Rennes installed the complete climate control system for Neele-Vat’s warehouse (approximately 38,000 m2) and office (approximately 7,000 m2). Its scope covered everything from climate control systems to lighting and power installations, and from design and engineering through to installation. “To ensure an optimum working environment and high sustainability ratings, we installed two large air-to-water heat pumps to cool and heat the offices,” says Peter Jacobs, Project Manager at Van Rennes. “The heat pumps supply not only the high-efficiency air handling units, but also the chilled ceilings. The entire office is fitted with chilled ceilings incorporating lighting and ventilation. In the warehouse office, where drivers report in, a standalone air-to-water heat pump system with fan coil units has been installed, while in the warehouse itself only the logistics zone is climate-controlled. We have installed several radiant tube heaters in the areas where goods are brought in. These are switched on only on extremely cold days.”

The heat pumps supply not only the high-efficiency air handling units, but also the chilled ceilings.

Comprehensive controls and monitoring system

A total of five air handling units have been installed, Jacobs says: three on the roof and two in the plant room. “All the units feature heat recovery via either a rotary heat exchanger or a cross-flow heat exchanger. Another sustainable feature is the Priva monitoring and control system and building management system installed in the new building.” Colleague and Project Manager David Middelkoop adds: “All the power distribution boards are fitted with kWh meters, and their readings are monitored through the building management system. This enables Neele-Vat to see exactly how much energy is being used and plan accordingly. Sustainable DALI LED lighting has also been installed throughout. The lighting in the racking aisles is linked to DALI motion detectors. When no movement is detected, the luminaires automatically dim to 10%.” The offices are fitted with 120 motion detectors, which are also controlled by the DALI system and linked to the Priva control system. The corridor lighting is linked to Priva too, so it can be switched on and off. “As soon as the alarm is activated in the evening, all the lights switch off automatically, preventing energy waste.”

The climate control systems, solar shading and lighting in the open-plan offices and meeting rooms can easily be controlled using local controllers and a wall-mounted control panel. “Another notable feature of the head office is the floor box system, which will allow flexible layouts in the future,” says Middelkoop. “The floor boxes had to be installed before the sand-cement screed was poured, so we were on site at a very early stage.”

The rooftop plant currently stands alone, but will soon be joined by a large number of solar panels.

Offices 16 metres above ground

To avoid large quantities of cabling, an extensive busbar trunking system with tap-off boxes was selected for the warehouse, Middelkoop says. “The offices are also supplied from here, with the ground floor approximately 16 metres (!) above ground.” Jacobs adds: “The office is on the roof of the warehouse, which made the delivery of materials and the fit-out work complex. We brought as many materials as possible inside by crane and through the windows. De Vries en Verburg Bouw also provided transport equipment, including a goods lift, which all the parties made extensive use of.” The new distribution centre and head office was completed at the end of the second quarter. However, Van Rennes has not yet left Pernis. “Solar panels are currently being installed across the roof of the new building,” says Middelkoop. “We are installing separate distribution boards for these, which will feed the generated electricity back into the busbar trunking system. This will make the energy supply as sustainable as possible too.”

A business enquiry for Schilt bedrijven? Get in touch

Who worked on it

Neele-Vat Rotterdam distribution centre in Rotterdam

  1. Ventilation systemsSchilt bedrijven
  2. clientNeele-Vat
  3. clientDudok Logistiek Vastgoed
  4. architectDesignlogic
  5. architectRoosRos Architecten
  6. architectHofmanDujardin
  7. Structural engineerAMB
  8. ContractorDe Vries en Verburg Bouw
  9. Building services adviceValstar Simonis
  10. Building servicesInstallatiebedrijf Van Rennes

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectNeele-Vat Rotterdam distribution centre
  • SubjectProjects
  • CompanySchilt bedrijven
  • CompanyNeele-Vat
  • CompanyDudok Logistiek Vastgoed
  • CompanyDesignlogic
  • CompanyRoosRos Architecten
Share this article

Advertisement

Follow Installatie & Bouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.