Noordzicht, Eindhoven | ‘Tailor-made’ air handling unit for Noordzicht in Eindhoven

Over the years, a huge number of (office) buildings have been constructed in the Netherlands. After 25 to 30 years, these buildings are due for a thorough ‘update’ to meet today’s requirements and expectations. The structural framework can last for many years yet, but the building’s ‘interior’ needs a major renovation. Often, entire floors are stripped back and refitted. At such times, decisions must also be made about the various components of the building services installation, including the air handling units: should they be refurbished and possibly ‘upgraded’, giving them many more years of service? Or should they be replaced? Above the concourse of Eindhoven NS Station is an office (Noodzicht), where the latter option was ultimately chosen…
“First, we brought the loose components inside, for the sections that had to be assembled on site. The remaining unit sections were placed on the roof, as there wasn’t enough room to put everything in the plant room at once.”

Strukton Worksphere in Son was one of the companies invited to develop a plan to refurbish the office floors and ‘upgrade’ the air handling system. Initially, the intention was to add heat recovery to the existing Holland Heating AHU, which was around 30 years old. Options also had to be put forward for making the fans more energy-efficient. To determine the best approach, Strukton and Systemair surveyed the site. “This revealed not only that the plant room was extremely cramped, but also that the AHU was unsuitable for fitting a heat recovery system without a return air filter,” says Arjan van Bladel, Account Manager at Systemair. “So we started looking beyond the plant room. One proposal was to install a heat recovery section outside on the roof, but ultimately the solution was a ‘tailor-made’ air handling unit built from standard solutions. Strukton was quickly convinced. Among other things, the AHU’s energy class A rating made it eligible for a subsidy, keeping costs down.” Systemair was commissioned to supply a new air handling unit in nine sections, two of which had to be assembled on site because of the limited access opening. “We drew up a transport plan together with Strukton,” says Van Bladel. “The air handling unit was manufactured at our factory in Waalwijk.”
Thorough preparation
Noordzicht houses several NS departments, including train traffic control. As trains run around the clock, the building is also in use 24 hours a day, 7 days a week, Van Bladel explains. “This placed specific requirements on the work, as did the building’s location. Lifting operations were not permitted on the railway side or at either end of Noordzicht, so all the installation components had to be brought in from the square in front of the building, which is the bus station. However, the mobile crane could only be assembled once the last bus had left, just after midnight. Everything had to be cleared away again by 6.00 am. Thorough preparation was therefore essential.”
In the morning, four Systemair fitters, assisted by a transport partner of Strukton, began assembling the unit sections. Over the following days, the remaining sections were also brought inside, positioned and connected.

The night of 15 to 16 October was finally the moment. During the day, a Strukton subcontractor had dismantled the old AHU and placed it on pallets on the roof. “We had also determined the lifting sequence for the new AHU in advance,” says Van Bladel. “First, we brought the loose components inside, for the sections that had to be assembled on site. The remaining unit sections were placed on the roof, as there wasn’t enough room to put everything in the plant room at once. The bases for both the rotary heat exchanger section and the steam humidification section had already been assembled at our factory, to shorten the project lead time and reduce the amount of work required on site. In the morning, four Systemair fitters, assisted by a transport partner of Strukton, began assembling the unit sections. Over the following days, the remaining sections were also brought inside, positioned and connected. By the end of the week, the new AHU was operational.”
Text: Lieke van Zuilekom | Image: Systemair
Featured image: “Lifting operations were not permitted on the railway side or at either end of Noordzicht, so all the installation components had to be brought in from the square in front of the building, which is the bus station.”
A business enquiry for Systemair? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectNoordzicht
- ThemeHealthy indoor air
- SubjectProjects
- CompanySystemair