Stadium/Galgenwaard complex | Utrecht

Galgenwaard Onroerend Goed B.V. is investing in a sustainable future
One of the largest ‘solar parks’ in the Netherlands is located on the roof of the stands at Galgenwaard stadium, part of Galgenwaard Onroerend Goed B.V. and home to FC Utrecht. HOMIJ Technische Installaties recently installed the technical infrastructure here for 3,380 solar panels, generating 817,000 kWh per year. This is enough to make not only the football-related areas but also the sushi restaurant, pharmacy, Zuid corner office and ROC Midden-Nederland energy-neutral, as well as part of the central hall of the Noord corner office. Any surplus electricity is fed back into the grid.
All readings from the kWh meters are displayed on a large screen (Energiespiegel) in the central reception hall of the stadium’s main building, clearly showing all the solar panels and their output.

The 3,380 panels required 30 kilometres of cable and 23 inverters on the DC side, converting solar energy from DC to AC. On the AC side, HOMIJ’s Vianen branch installed a further 2,635 metres of cable in five different sizes, as well as numerous cable routes and heavy-duty copper Busduct power components. “To connect all the cables, we modified a main distribution board and installed eight new switchgear and distribution assemblies (sub-distribution boards),” says Erik van Hal, Account Manager at HOMIJ Technische Installaties. “Eight kWh meters measure and record the solar panels’ energy output, voltage and power, as well as the amount of solar electricity consumed by each tenant in the stadium/Galgenwaard complex. We called on BRControls to supply the switchgear and distribution assemblies and kWh meters, and we regularly work with them on projects.”
Clear, detailed insight
“Because the solar panels generate such a large amount of electricity, we engineered and supplied 400-amp switchgear and distribution assemblies with a breaking capacity of 15 kA (kiloamperes), fully compliant with the IEC-EN61439 standards,” says José Gomez, Account Manager for electrical distribution boards at BRControls. “At HOMIJ’s request, we connected the kWh meters in the distribution boards to the building management system above them. For this, we used our powerful BRC-45 controller. All readings from the kWh meters are displayed on a large screen (Energiespiegel) in the central reception hall of the stadium’s main building, clearly showing all the solar panels and their output. This gives Galgenwaard staff greater insight and also raises energy awareness among stadium visitors.”

Each control cabinet is equipped with a new BRC-46 central primary system controller, including a high-speed processor, UPS-backed control power-down and an internal SQLite database management system for data storage and analysis.
Step-by-step decarbonisation
The solar panel installation is part of a step-by-step sustainability programme at Galgenwaard, which also includes the installation of energy-efficient LED lighting and the replacement of the fire alarm control panel and control systems, says John Koekoek, manager of the Galgenwaard complex. “Both the fire alarm system and the control systems date from 2001 and had become so outdated that, if a fault occurred, it was no longer possible to replace the components. Simply because they are no longer manufactured. Replacing them is therefore essential to ensure the systems continue to work in the future and to simplify their management. To get this right, we called on HOMIJ, which has been responsible for maintaining our technical installations since 2006.”
Reliable, user-friendly control system
To control heating, cooling, air handling and lighting in the stadium effectively, Galgenwaard and HOMIJ sought a reliable, user-friendly control system that would make it easy to monitor how the installations were working. John Koekoek: “In future, we want to see at a glance which systems are running, at what capacity and where any problems are occurring. This will enable us to tailor management and maintenance and to track all key parameters and readings over the long term: how have processes performed over the years? When have faults occurred? And how are the systems operating compared with the same period one, five or ten years ago? We also want to be able to manage the systems remotely, something that BRControls’ control technology is ideally suited to.”
The BRC-46 is fully IP-based and enables connections over Ethernet.

Over the coming months, the existing control cabinets will be converted, fine-tuned and recommissioned in phases, one stand section at a time. Erik van Hal: “There are 18 control cabinets in the various rooms around the stadium, currently using Priva and Siemens control technology. This control system will be replaced with BRControls technology. Using a bus line, we will make all relevant system information visible on large screens. This includes, for example, the commissioning processes for heating, cooling and air handling, the operation of the heating pumps and their associated energy consumption. This information will enable us to optimise the systems and control technology.”
Modern and web-based
HOMIJ is responsible for all cabling between the substations and assists with converting the control cabinets, while BRControls is responsible for replacing the control technology and installing it on site, says Harry Peters, Sales Manager at BRControls. “The outdated building management system, which still runs on an old Windows platform, is being replaced with a modern, web-based control system from BRControls. We are equipping each control cabinet with a new BRC-46 central primary system controller, including a high-speed processor, UPS-backed control power-down and an internal SQLite database management system for data storage and analysis. The BRC-46 is fully IP-based and enables connections over Ethernet. This will allow HOMIJ to make significant savings on cabling and installation hours, while also enabling remote management and maintenance. The modular BRC-46 central primary system controller is freely programmable and includes a range of web visualisation options. This makes it easy to monitor all the connected climate control systems in the Galgenwaard complex and also helps us create a better indoor environment in the stadium and offices while keeping energy consumption to a minimum.” With this upgrade, Galgenwaard Onroerend Goed B.V. is preparing for future developments and the sustainability of the entire complex. The new control technology is due to be commissioned in February/March 2019.
Words: Lieke van Zuilekom | Image: BRControls
Featured image: One of the largest ‘solar parks’ in the Netherlands is located on the roof of the stands at Galgenwaard stadium, part of Galgenwaard Onroerend Goed B.V. and home to FC Utrecht.
Question about this story? Ask your question
Who worked on it
Stadion Galgenwaard in Utrecht
- technische infrastructuurHOMIJ Technische Installaties
- control technologyBRControls
Keep following this
Get an email when a new story is published. No account needed.
- ProjectStadion Galgenwaard
- ThemeEnergy generation and distribution
- SubjectProjects
- CompanyHOMIJ Technische Installaties
- CompanyBRControls
- CompanySiemens