‘State-of-the-art lifts and escalators are showcased to full effect’

‘State-of-the-art lifts and escalators are showcased to full effect’

Step into the lift at nhow Amsterdam RAI and you can look forward to a fast, comfortable journey up through the building. In no time at all, you are on the top floor, yet it feels as if you have not moved. These high-rise lifts, and everything involved in their installation, are the work of Schindler Liften B.V..

“In 2014, Pleijsier Bouw, the contractor and our client, asked us to help develop and cost the lift solution for the hotel,” says Schindler key account manager Marc Twickler. Maarten Bijl, product and marketing manager at Schindler, adds: “We advised on the most suitable type of lift. Our recommendations also covered the number, size and speed of the lifts. The complex core, with two lift shafts, presented a major challenge.”

Hybrid solution

Several constraints informed the chosen lift solution. For example, there could be no machine room on the building, in order to stay within the maximum building height of 91 metres. “We opted for a hybrid solution,” says Twickler. “Part of the lift installation was machine-room-less.” There are seven guest lifts in total, running from the ground floor to the 23rd floor. There are also three back-of-house lifts, running from floor -1 to floor 23. In addition, two escalators connect the ground and first floors, and two glass shuttle lifts serve the car park.

View into the lift shaft.

Sustainable and comfortable

The lift selected for this high-profile building is the Schindler 5000. Its defining features include circularity and energy efficiency. Twickler says: “The vast majority of its components can be reused. The Schindler 5000 is also highly energy-efficient and achieves the maximum credits for the hotel’s BREEAM rating with its A energy label. Its regenerative drive system also contributes to its sustainable credentials. Depending on the load, energy is generated when the lift travels both up and down. That energy is fed back into the power supply.” In terms of comfort and appearance, the lifts are a far cry from standard models. They travel at 3 metres per second, yet passengers barely notice the speed. The lifts are also virtually vibration-free and silent.

Predictive maintenance

“Cloud solutions are an important development at Schindler,” stresses Bijl. “The lifts at nhow Amsterdam RAI are connected to the cloud via a gateway. We can continuously monitor their status and behaviour, and analyse the data using software. If we detect anything unusual, we can respond quickly. We can also tailor maintenance much more precisely and efficiently to the condition of the installation components. We call this predictive maintenance. It is part of Schindler Ahead, our programme of digital products and services.”

All the lifts were installed between September 2018 and December 2019.

Climblift

In September 2018, when the building had reached one third of its final height, Schindler began installing the back-of-house lifts. These were used as Climblifts. Twickler explains: “The lifts climbed along with the core, initially up to the tenth floor. They were then inspected and used as construction lifts.” After installing the back-of-house lifts, Schindler installed the other lifts and escalators. All the installations have now been commissioned and connected to the building management system.

Good collaboration

Twickler looks back on the project with great satisfaction: “The collaboration with the contractor and other parties went particularly well. We took on this project together and worked together to find solutions.” Bijl adds: “We operate in more than a hundred countries and have seen many technical and architectural feats. This is certainly a very special project in the Netherlands. We are extremely proud to have contributed to this fantastic building. Our state-of-the-art lifts and escalators are showcased to full effect.” 

A business enquiry for Schindler Nederland? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectProjects
  • CompanySchindler Nederland
Share this article

Follow Installatie & Bouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.