‘We work out 90% of our projects in BIM’

In housing projects, buyers often have a choice of different options for sanitaryware, kitchens, mechanical services and electrical installations. If these choices can be incorporated into the BIM model during the design phase and translated into prefabrication drawings, significant time can be saved on site. This is especially true when the design teams use the latest version of Stabicad for Revit, which makes it easy and quick to copy similar installation options to other homes, together with the associated information. This is right up the street of Wierda Projecttechniek BV, which carries out almost all its projects using the BIM method.

Wierda Projecttechniek BV offers a comprehensive range of electrical services. A permanent team of employees designs, calculates, supplies and installs lighting and power systems, as well as systems for data and telecommunications, access control, home automation, and intruder and fire detection. In addition to the healthcare sector, the Emmeloord-based specialist focuses mainly on large-scale housing developments, from small projects involving single-family homes to large projects with apartment blocks, sometimes combined with car parks. “We work out more than 90% of these projects in BIM/Stabicad for Revit,” says Jeffrey Hofstee, draughtsman/BIM engineer at Wierda Projecttechniek BV. “Not only because this enables prefabricated shell construction, where the factory can easily extract all the necessary information from the 3D model, but also because we can generate our variations and options from the model at the touch of a button.”
Show home
“Our client usually provides us with a basic Revit model showing roofs, walls, doors and windows, which we use to develop our elements in 2D and 3D,” says Hofstee. “This is followed by various review and coordination meetings, during which we optimise our installations.” Wierda Projecttechniek BV also always creates its own BIM model, he says, in which the electrical provisions are worked out in detail. This includes socket outlets, conduits and switches, which can easily be downloaded from the MEPcontent library. “In most cases, we design one show home in which the client can indicate their preferences. These might include the location of additional lighting points, switches and sockets, as well as an extension or an additional façade option. We then work out all the house types in detail, including the buyer options. That way, we avoid any surprises during construction.”
Variation codes

“Once a model is complete and approved, we can export these variation codes at the touch of a button.”
Both the client’s electrical provisions and the buyers’ preferences are assigned a code linked to a product price. Hofstee says: “Once a model is complete and approved, we can export these codes at the touch of a button, including the associated prices, so we know exactly what it will cost to build each home. We can generate variation schedules for around 80 homes in half an hour. That’s a huge difference from a few years ago, when we sometimes spent days calculating and recalculating the costs.”
Material scheduling
As well as variation codes and price lists, Wierda Projecttechniek BV also generates installation schematics from the BIM model, along with schedules of floor and wall openings. “Our next goal is to generate materials lists,” says Hofstee. “That way, we can see all the electrical installation components in the homes and send a purchase list for each home to the technical wholesaler. All directly from the BIM model, saving time and avoiding communication errors.”
Recent BIM projects by Wierda Projecttechniek BV include the construction of 41 homes on the former Knorr factory site in Loosdrecht, as well as 23 homes in Scherpenzeel, 42 homes in Bodegraven, 48 homes in Soesterberg and 66 homes in Hoevelaken. “We’re currently busy preparing 46 homes in Putten, where we want to make even greater use of BIM,” says Hofstee. “Among other things, by focusing on plug-and-play installations, with all electrical conduits, wires, junction boxes and cavity wall boxes supplied directly by the factory and installed as prefabricated units. This saves our installers on site a considerable amount of time, gives them greater flexibility and reduces rework. Plug-and-play installations are also much more environmentally friendly, reusable and recyclable. In the future, they will become increasingly common.”