Optimal gas distribution for research laboratories

The Feringa Building houses a wide range of laboratories. As a subcontractor to De Groot-Lammerink, Dräger is responsible for designing and supplying/installing the distribution systems for high-purity gases in these spaces. Xander te Loo, business unit manager workplace infrastructure at Dräger Nederland, explains the distinctive nature of the work.

Since 1889, Dräger has helped protect and support people and save lives around the world. It does so with a broad range of services and products, including breathing apparatus, medical devices, alcohol and drug detection equipment, personal protective equipment and gas distribution equipment. The latter product group will be used throughout the various physical, (bio)chemical and vibration-free laboratories that the Feringa Building will house once completed. Last summer, Dräger began installing the gas distribution systems used by PhD students, among others, for a range of materials research. The entire project is scheduled for completion by the end of 2023.
“The central and decentralised systems we install transport gases from the source through pipework to one of the points of use in the laboratories,” explains Te Loo. “As well as ensuring safe use, it is essential that the gases are supplied at optimum quality, pressure and capacity, and delivered in the right way. These processes must be closely controlled and monitored. The technologies we use take care of that.”
No prefabrication
Based on the design provided by the consultant, Dräger began work with highly detailed engineering of the systems required. They were then incorporated into a 3D Revit model to ensure seamless coordination with the other building services. Physical installation, including assembly, fitting and testing, could then begin. “All system components are assembled on site. We do not use prefabrication. When systems are built on skids, there is a risk of internal contamination of the gases. We do not want to take that risk. That is why everything is assembled in one go at the project site,” says Te Loo, who considers the Groningen project particularly special. “When completed, the Feringa Building will house one of the most extensive laboratory facilities in the country within the education sector. Dräger is therefore very proud to have contributed to the project, including by installing around 22 kilometres of pipework and fitting approximately 100 decentralised gas pressure regulation panels. Once the work is complete, we will be pleased to add it to our list of references.”
Question about this story? Ask your question
Who worked on Feringa Building
- mechanical and electrical installationsDe Groot-Lammerink Installatiecombinatie B.V.Mentioned in Dynamic lighting control for Feringa Building
- complete lighting installationSignum Meet- en RegeltechniekMentioned in Dynamic lighting control for Feringa Building
- air handling unitsAL-KO LuchttechniekMentioned in Feringa Building, Groningen: 21 air handling units process around one million kilos of air per hour
- specificationArcadisMentioned in Feringa Building, Groningen: 21 air handling units process around one million kilos of air per hour
- gas distribution systemsDrägerIn this story
- pluggable systems
IsolectraMentioned in Plug-and-play lighting and power installations for Feringa Building Groningen: Smart & fast - ClientRijksuniversiteit Groningen (RUG)Mentioned in Plug-and-play lighting and power installations for Feringa Building Groningen: Smart & fast
- ArchitectEctor HoogstadMentioned in Plug-and-play lighting and power installations for Feringa Building Groningen: Smart & fast
Keep following this
Get an email when a new story is published. No account needed.
- ProjectFeringa Building
- SubjectBuilding services engineering
- CompanyDräger