Building services engineering

SPOT residential towers to be equipped with complete ATES system

Text Desiree PenningsImage Roodenburg

Binnen SPOT komen zeven woontorens met 1.090 woningen.
Binnen SPOT komen zeven woontorens met 1.090 woningen.

SPOT is part of Amsterdam’s largest urban transformation project, in the heart of the Amstel III business park. Where there were once only office buildings, three plots have been cleared for seven residential towers containing 1,090 homes. There will also be space for offices, shops, restaurants, sports facilities and a primary school. Installation company Roodenburg is providing the complete ATES system for heating, cooling and domestic hot water. 

Everything is due to be operational in the first quarter of 2026.

This particularly sustainable installation uses a doublet well system with a total capacity of 240 m3/h for the heat pump plant. In addition, a central district heating connection supplies the energy for producing domestic hot water in the delivery sets.

The technical rooms for heating and cooling generation are located in the basement of the car park. A complete distribution network runs from these rooms to all the residential towers. Riser pipes have been installed in each tower to provide connections on every floor. Roodenburg is equipping all the homes with an advanced delivery set, installed in the meter cupboard or storage room.

As well as the homes, Roodenburg is also connecting the commercial spaces to delivery sets. Much of the pipework was supplied prefabricated by a specialist department within the company.

Heat and cooling are distributed from the central plant room to all the homes.

Final construction phase

The project began in 2018, when Roodenburg carried out a preliminary study into the optimum application of the system. The findings were incorporated into the subsequent design of the area. The construction phase began in June 2023. The final tower is expected to be completed in early 2026. “We’re currently working on the last two towers,” says project manager Bryan Hoogvliet. “After the summer construction holiday, we’ll start the fit-out phase and these towers will also be equipped with delivery sets. Then comes the final, but important, phase: commissioning all 1,090 homes. This phase will continue until March 2026.”

As no permanent transformer connection is yet available, district heating is being used initially. Once the transformer is connected, the system can switch to the heat sources.

Heat recovery saves a great deal of energy.

A way of working of its own

Good communication with the client and contractors is essential to the success of a project. Challenges inevitably arise during construction, including coordinating schedules and dealing with weather conditions, as well as carrying out work around systems that have already been installed. Safety is a top priority for Roodenburg. Clear agreements have therefore been made with the contractors on working safely on site.

The client for the installation company on this project is Eteck, a supplier of sustainable heat. The two companies have worked together successfully on ATES systems on several previous occasions. What makes SPOT distinctive is that two contractors are involved, requiring close cooperation and coordination. “To deliver a properly functioning ATES system, we were brought into an existing construction team,” says Hoogvliet. “There’s always a period of getting to know each other at first, but in the end we find common ground. Every company has its own way of working, but we share the same goal: creating high-quality, sustainable homes. And at SPOT, we’ll certainly achieve that!”

Question about this story? Ask your question

Who worked on SPOT

  1. Purge filterRoodenburgMentioned in The underground section of SPOT’s ATES system presents a range of challenges
  2. supplier of sustainable heatEteckIn this story
  3. control system cablingPMDKMentioned in Reliable building solutions through expert installation of control systems

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectSPOT
  • ThemeGas-free heating and cooling
  • SubjectBuilding services engineering
  • CompanyEteck
Share this article

Follow Installatie & Bouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.