Projects

Depot Boijmans Van Beuningen: An optimal indoor climate within very tight limits

Begin november is de laatste spiegel op de gevel van Depot Boijmans Van Beuningen gemonteerd. Daarmee is de buitenzijde van het eerste publiek toegankelijke kunstdepot ter wereld gereed. (Beeld: MVDRV).
Begin november is de laatste spiegel op de gevel van Depot Boijmans Van Beuningen gemonteerd. Daarmee is de buitenzijde van het eerste publiek toegankelijke kunstdepot ter wereld gereed. (Beeld: MVDRV).

The final mirror panel was installed on the façade of Depot Boijmans Van Beuningen in early November. The exterior of the world’s first publicly accessible art storage facility is now complete.

The final fit-out work is still under way inside. The climate control systems and their associated controls are also being thoroughly tested, so that more than 151,000 unique collection items can be moved in between December and April. The museum will then undergo a period of trial operation, ahead of the Golden Opening in autumn 2021.

Depot Boijmans Van Beuningen has a floor area of 15,000 m², stands 39.5 metres tall and has a footprint of Ø 40 metres, widening towards the top to Ø 60 metres. The ground floor comprises a welcoming entrance area with a museum shop and coffee bar. This floor also houses the art handling facilities, for packing, acclimatisation, quarantine, loading and unloading. All the storage rooms, exhibition spaces, the expertise centre and the cinema are located on the 1st to 6th floors, around a central atrium with a glass roof. This allows as much daylight as possible to enter.

The project uses the BRT-24 modular room control system, including a touchscreen.

Five climate zones

Storing and preserving the collection items places specific demands on the building services. All risks of fire, burglary and water damage must be prevented, and air conditions must be optimal. Organic and inorganic objects, photographs and metal objects, for example, have different climate requirements, so the depot is divided into 5 climate zones. “Strict temperature and relative humidity limits apply in these zones, and compliance must be demonstrated,” says Alexander Wassink, Operations Manager at BRControls. In the ‘standard’ storage rooms, for example, the required summer temperature is 18-22°C; relative humidity may fluctuate between 52-55%. In winter, the requirements are 16-20°C and 47-52%. “There are also rooms where temperature may deviate by no more than 0.5-1°C and relative humidity by no more than 2%. A carefully balanced, continuous control of cold or warm air, humid air and dry air is needed to ensure these conditions are maintained at all times, including when visitor numbers are high and/or in damp weather. Our advanced measurement and control technology makes an important contribution.”

Real-time data

The project uses the BRT-24 modular room control system, including a touchscreen, Wassink explains. “The room controls are mounted on the walls of the various spaces and connected to our new BRN-15 room controllers. The data collected by the room sensors is not only available 24/7 and monitored through our web-based building management system, but also shared in real time on the touchscreens. If the temperature or relative humidity unexpectedly moves outside the permitted limits, an alarm is triggered automatically. This means that appropriate action can be taken immediately.”

The depot is one of the first projects to use BRControls’ BRN-15 room controllers.

Latest room controllers

“The depot is one of the first projects to use our BRN-15 room controllers,” says Gert Balder, Senior Account Manager at BRControls. “The BRN-15 is a modular, freely programmable IP-based secondary control system that can handle even the most complex room control requirements. In addition to museums, the BRN-15 is ideally suited to applications such as cleanrooms, where maintaining the right temperature and humidity is essential.”

Depot Boijmans Van Beuningen was designed by MVRDV. BAM Bouw en Techniek is responsible for delivering the iconic new building. Working closely with the contractor and building services consultant Royal HaskoningDHV, BRControls selected and supplied the most suitable measurement and control technology for the various spaces.      

Question about this story? Ask your question

Wie aan Depot Boijmans van Beuningen werkte

  1. building services consultantsRoyal HaskoningDHVMentioned in Rotterdam, Depot Boijmans van Beuningen | Building services in the service of art
  2. lichtregelsysteemHelvarMentioned in Intelligent lighting control system guides visitors
  3. climate controlValk AircoMentioned in Museum Boijmans van Beuningen | Hands-on approach to powerful climate concepts
  4. contractorCitadelMentioned in Museum Boijmans van Beuningen | Hands-on approach to powerful climate concepts
  5. heat pumpsMitsubishi ElectricMentioned in Museum Boijmans van Beuningen | Hands-on approach to powerful climate concepts
  6. contractorBAM Bouw en TechniekIn this story
  7. meet- en regeltechniekenBRControlsIn this story
  8. dakkappen en buitenluchtroostersSmitsairMentioned in Roof cowls give Depot Boijmans van Beuningen room to breathe

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectDepot Boijmans van Beuningen
  • ThemeHealthy indoor air
  • SubjectProjects
  • CompanyBAM Bouw en Techniek
  • CompanyBRControls
Share this article

Follow Installatie & Bouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.