Museums usually display only a small part of their rich collections, but next year Museum Boijmans Van Beuningen is breaking with that tradition. The Rotterdam museum is inviting visitors to discover the entire collection of more than 150,000 works of art in its new depot. Visitors can watch conservation work in progress and explore the world behind the museum. But don’t let the warm welcome and spectacular architectural design by MVRDV distract you: preserving the art treasures is the top priority. The building services are there to support that goal, explain installation consultants Marco Maas and Yilmaz Akbina of Royal HaskoningDHV.

Storing and preserving such a valuable art collection places special demands on the building services. Every risk of fire, break-in and water damage must be prevented, and air conditions must be optimal. “Water-bearing pipes in storage areas are a no-go,” says Maas. “The rooms also have to meet stringent climate requirements. Different climate specifications have been defined to store organic and inorganic objects, photographs and metal objects as efficiently as possible.” The air conditions in each storage area are tailored to the objects it houses, and strict climate ranges are maintained. “For example, the ‘standard’ storage areas must be kept at 18-22°C in summer, with relative humidity allowed to fluctuate between 52 and 55%; in winter, the requirements are 16-20°C and 47 to 52%. These conditions are continuously monitored in every storage area.” The building is heated and cooled efficiently using an aquifer thermal energy storage system.

Ventilation

The art storage areas are also ventilated only sparingly. “The standard air change rate is no more than 0.2 1/h,” Maas and Akbina explain. Fresh air is pre-treated on the 6th floor, then transported through the shafts beside the stairwells to the mezzanine on the 1st floor, where it undergoes further treatment. Supply ducts then carry the conditioned air along the façades to the storage areas. “The air is not actively extracted from the art storage rooms. An air transfer system moves it to the atrium, where the ventilation air is extracted centrally, allowing heat and moisture to be recovered and reused.”

The air handling units for further treatment are on the 1st floor; the pre-treatment air handling units and the restaurant plant are on the 6th floor.

Infrastructure

Almost all the vertical infrastructure, including electrical services, the atrium air supply, water pipes and heating pipes, is located in the heart of the building and runs through shafts on either side of the 35-metre-high atrium to the plant rooms. “The building services are housed in mezzanines, intermediate floors on the 1st and 6th floors,” says Akbina. “The main electrical installations, such as the main distribution board, emergency power supply and MER/SER rooms, are located between the ground floor and the 1st floor.” PV panels generate electricity from solar energy.

Safety

Akbina, an electrical engineer, explains that special safety measures have also been taken with regard to the electrical services. “For example, a large battery can take over the most important functions without interruption if the mains power fails. When someone enters a storage area, the lights come on in both that area and the adjacent zone as soon as movement is detected. And when no further movement is detected, not only do the lights go out, but the socket outlets are also de-energised. The storage area is then no longer live, reducing the risk of fire and short circuits.”

Water management

Rainwater downpipes run between the concrete building envelope and the mirrored façade. Maas explains: “Rainwater from the rooftop forest is conveyed to the prefabricated basement tanks using a vacuum drainage system.” Leaves and twigs are screened out before the water enters the tanks, so it is relatively clean. When the toilets need water, the rainwater is pumped through a three-stage filter: first a coarse filter, then a fine filter, and finally a carbon filter that removes odours and colour. Measures such as these make Depot Boijmans Van Beuningen efficient in both energy and environmental terms.   

A business enquiry for Maas & Hagoort? Get in touch

Wie aan Depot Boijmans van Beuningen werkte

  1. building services consultantsRoyal HaskoningDHVIn this story
  2. lichtregelsysteemHelvarMentioned in Intelligent lighting control system guides visitors
  3. climate controlValk AircoMentioned in Museum Boijmans van Beuningen | Hands-on approach to powerful climate concepts
  4. contractorCitadelMentioned in Museum Boijmans van Beuningen | Hands-on approach to powerful climate concepts
  5. heat pumpsMitsubishi ElectricMentioned in Museum Boijmans van Beuningen | Hands-on approach to powerful climate concepts
  6. contractorBAM Bouw en TechniekMentioned in Depot Boijmans Van Beuningen: An optimal indoor climate within very tight limits
  7. meet- en regeltechniekenBRControlsMentioned in Depot Boijmans Van Beuningen: An optimal indoor climate within very tight limits
  8. dakkappen en buitenluchtroostersSmitsairMentioned in Roof cowls give Depot Boijmans van Beuningen room to breathe

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectDepot Boijmans van Beuningen
  • SubjectProjects
  • CompanyRoyal HaskoningDHV
  • CompanyMaas & Hagoort
Share this article

Follow Installatie & Bouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.